PROJECT ID |
PROJECT |
TYPE |
PROJECT MANAGER |
STATUS |
| AIRPORT BLVD SIDEWALK | SIDEWALK PROJECTS | Eric Erickson
eerickson@seminolecountyfl.gov 407-665-5666 |
ACTIVE | |
|
From: US 17-92
To: SANFORD AVE
Scope: THIS PROJECT WILL CONSTRUCT 6,000 LINEAR FEET OF SIDEWALK, MISSING GAPS ON NORTHSIDE AND REPLACING CRACKED AND/OR SUB-STANDARD EXISTING SIDEWALK ON AIRPORT BLVD FROM U.S. HWY 17/92 TO SANFORD AVE. Phases:
Design Start: 5/2008 End: 4/2009
Land Start: 4/2008 End: 12/2009 Construction Start: 10/2009 End: 3/2010 |
||||
| ALOMA AVE AT RED BUG LAKE RD PEDESTRIAN OVERPASS | PEDESTRIAN OVERPASSES / UNDERPASSES | David Martin
dmartin02@seminolecountyfl.gov 407-665-5610 |
ACTIVE | |
|
From: N/A
To: N/A
Scope: CONSTRUCT A PEDESTRIAN OVERPASS OVER RED BUG LAKE RD AT ALOMA AVE TO IMPROVE PEDESTRIAN SAFETY. Phases:
Design Start: End:
Construction Start: End: |
||||
| ALTAMONTE CITY COUNTY SHARED PEDESTRIAN OVERPASS | UNIQUE MAJOR PROJECTS | Antoine Khoury
akhoury@seminolecountyfl.gov 407-665-5768 |
ACTIVE | |
|
From: N/A
To: N/A
Scope: CITY OF ALTAMONTE SPRINGS PROJECT FOR PEDESTRIAN OVERPASS Phases:
Road Construction Start: End:
|
||||
| ANCHOR RD DRAINAGE IMPROVEMENTS | SECONDARY SYSTEM STORMWATER PROJECT (SALES TAX) | Rolando Raymundo
RRaymundo@seminolecountyfl.gov 407-665-5715 |
ACTIVE | |
|
From: SR 436
To: MELODY LN
Scope: DRAINAGE IMPROVEMENTS INCLUDING PIPING OF DITCH, INSTALLATION OF INLETS, AND WATER QUALITY TREATMENT. MISC. ROADWAY IMPROVEMENTS ALSO INCLUDED Phases:
Design Start: 6/2005 End: 11/2008
Land Start: 2/2007 End: 9/2009 Construction Start: 12/2008 End: 11/2009 |
||||
| ARRA HOWELL BRANCH RD | ARTERIAL/COLLECTOR PAVEMENT REHABILITATION | Mike Van Der Heyden
mvanderheyden@seminolecountyfl.gov 407-665-5748 |
ACTIVE | |
|
From: COUNTY LINE
To: SR 436
Scope: THE OVERALL PROJECT WILL INCLUDE PAVEMENT REHABILITATION FOR HOWELL BRANCH ROAD PAVEMENT REHABILITATION - FROM COUNTY LINE TO ENSOR TERRACE FOR SEMINOLE COUNTY WHICH WILL INCLUDE MILLING AND RESURFACING ROADWAY SURFACE, INSTALLATION OF TRAFFIC SIGNAL LOOPS AND CONTROLS, AND REPLACEMENT PAVEMENT MARKINGS. FLORIDA DEPARTMENT OF TRANSPORTATION AGREEMENT # 426328-1-58-01 Phases:
Road Construction Start: 11/2009 End: 12/2009
|
||||
| ASPHALT SURFACE AND PAVEMENT MANAGEMENT | ARTERIAL/COLLECTOR PAVEMENT REHABILITATION | Harry Raysin
hraysin@seminolecountyfl.gov 407-665-2839 |
ACTIVE | |
|
From: VARIOUS LOCATIONS
To: VARIOUS LOCATIONS
Scope: ASPHALT OVERLAY, FULL DEPTH RECLAMATION, AND VARIOUS METHODS OF ASPHALT SURFACE REFURBISHMENT THAT ARE APPLIED TO SEMINOLE COUNTY`S PAVED ROAD NETWORK. THIS INCLUDES LOCAL ROAD RESURFACING AND REHABILITATION THAT MAY INVOLVE RECONSTRUCTION ACTIVITY. THIS ALSO INCLUDES RESURFACING OF ARTERIAL/COLLECTOR ROADS NOT INVOLVING THE ROADWAY BASE. Phases:
Road Construction Start: 10/2007 End: 9/2014
|
||||
| BEAR GULLY DRAINAGE IMPROVEMENTS | SECONDARY SYSTEM STORMWATER PROJECT (SALES TAX) | Robert Walter
RWalter@seminolecountyfl.gov 407-665-5753 |
ACTIVE | |
|
From: HOWELL BRANCH RD
To: GOLDENROD DR
Scope: DRAINAGE IMPROVEMENTS TO BEAR GULLY RD AND ADJACENT HOMES Phases:
Design Start: 7/2007 End: 1/2009
Land Start: 11/2008 End: 10/2010 Construction Start: 4/2009 End: 10/2010 |
||||
| BEAR GULLY LAKE ASSESSMENT | PRIMARY SYSTEM STORMWATER PROJECT | Kimberly Ornberg
kornberg@seminolecountyfl.gov 407-665-5738 |
ACTIVE | |
|
From: BEAR GULLY LAKE
To: BEAR GULLY LAKE
Scope: LAKE ASSESSMENT. Phases: |
||||
| BEAR LAKE RD AT BUNNELL RD MAST ARMS | TRAFFIC SIGNALS | Charles Wetzel Iii | ACTIVE | |
|
From: N/A
To: N/A
Scope: CONVERSION OF AN EXISTING SPAN WIRE SIGNAL TO MAST ARMS. Phases:
Road Construction Start: 3/2009 End: 8/2009
|
||||
| BIG TREE PARK TRAILHEAD | TRAILS | David Martin
dmartin02@seminolecountyfl.gov 407-665-5610 |
ACTIVE | |
|
From: BIG TREE PARK
To: BIG TREE PARK
Scope: DESIGN. PERMITTING, AND CONSTRUCTION OF A TRAILHEAD AT BIG TREE PARK. FLORIDA DEPARTMENT OF ENVIRONMENTAL PROTECTION AGREEMENT # T2705 Phases:
Design Start: 10/2007 End: 12/2009
Land Start: End: Construction Start: 2/2010 End: 6/2010 |
||||
| BIRD RD SIDEWALK | SIDEWALK PROJECTS | Eric Erickson
eerickson@seminolecountyfl.gov 407-665-5666 |
ACTIVE | |
|
From: LAKE DR
To: SEVILLE CHASE DR
Scope: THIS PROJECT WILL CONSTRUCT APPROXIMATELY 2,500 LINEAR FEET OF SIDEWALK ON THE EAST SIDE OF BIRD RD FROM LAKE DR TO SEVILLE CHASE DR. Phases:
Construction Start: 2/2010 End: 5/2010
|
||||
| BRIDGE REHABILITATION AND REPAIRS | UNIQUE MAJOR PROJECTS | ACTIVE | ||
|
From: COUNTYWIDE
To: COUNTYWIDE
Scope: THIS PROJECT WILL PROVIDE A FUNDING SOURCE FOR BRIDGE REHABILITATION AND REPAIRS TO CORRECT DEFICIENCIES IN COUNTY MAINTAINED VEHICULAR BRIDGES THAT WERE IDENTIFIED AND REPORTED TO THE COUNTY BY THE STATE OF FLORIDA. IN ADDITION, THE COUNTY IS REQUIRED TO COMPLETE AN INSPECTION AND REHABILITATION PROGRAM ON ALL PEDESTRIAN OVERPASSES OR TUNNELS. THIS PROJECT WILL PROVIDE A FUNDING SOURCE TO DESIGN AND CONSTRUCT REQUIRED REPAIRS. Phases:
Construction Start: 10/2009 End: 9/2014
Road Construction Start: 10/2008 End: 9/2013 |
||||
| BRUMLEY RD SIDEWALK | SIDEWALK PROJECTS | Ken Mickenberg
kmickenberg@seminolecountyfl.gov 407-665-5714 |
ACTIVE | |
|
From: SNOW VALLEY WAY
To: AVENUE H
Scope: THIS PROJECT WILL CONSTRUCT APPROXIMATELY 1,400 LINEAR FEET OF SIDEWALK ON THE NORTH SIDE OF BRUMLEY RD BETWEEN SNOW VALLEY WAY AND AVENUE H. INCLUDING 600 LF ON THE WEST SIDE OF AVE. H FROM BRUMLEY RD TO SNOWHILL RD Phases:
Construction Start: 6/2010 End: 7/2010
|
||||
| BUNNELL RD AND EDEN PARK AVE ROADWAY IMPROVEMENT PROJECT | MAJOR ROAD PROGRAM | Brett Blackadar
BBlackadar@seminolecountyfl.gov 407-665-5702 |
ACTIVE | |
|
From: WEST TOWN PKWY
To: ORANGE COUNTY LINE
Scope: THE PROPOSED PROJECT WILL HAVE A CURB AND GUTTER SECTION WITH TWO TRAVEL LANES (ONE IN EACH DIRECTION) AND ONE 12-FOOT CENTER TURN LANE. THE APPROXIMATE PROJECT LENGTH IS 2.0 MILES Phases:
Land Start: 4/2004 End: 6/2009
Road Construction Start: 1/2009 End: 4/2010 |
||||
| CASSEL CREEK STORMWATER FACILITY | PRIMARY SYSTEM STORMWATER PROJECT (JPP) | Robert Walter
RWalter@seminolecountyfl.gov 407-665-5753 |
ACTIVE | |
|
From: HOWELL CREEK BASIN
To: KEWANNE TR
Scope: 1.PRELIMINARY DESIGN OF REGIONAL STORMWATER FACILITY 2.FINAL DESIGN OF REGIONAL STORMWATER FACILITY. ST JOHNS RIVER WATER MANAGEMENT DISTRICT AGREEMENT # SG471AA ST JOHNS RIVER WATER MANAGEMENT DISTRICT ADDITIONAL ANTICIPATED AGREEMENT Phases:
Design Start: 6/2004 End: 2/2010
Construction Start: 10/2009 End: 9/2010 |
||||
| CHAPMAN RD WIDEN FROM 2 TO 4 LANES | MAJOR ROAD PROGRAM | Antoine Khoury
akhoury@seminolecountyfl.gov 407-665-5768 |
ACTIVE | |
|
From: SR 426
To: SR 434
Scope: THE PROJECT WILL WIDEN THE ROADWAY FROM TWO TO FOUR LANES. THE PROJECT LENGTH IS 1.7 MILES Phases:
Design Start: 9/2006 End: 6/2008
Land Start: 3/2008 End: 12/2013 Road Construction Start: 1/2011 End: 12/2012 |
||||
| CLUB II REGIONAL STORMWATER FACILITY | PRIMARY SYSTEM STORMWATER PROJECT (JPP) | Rolando Raymundo
RRaymundo@seminolecountyfl.gov 407-665-5715 |
MONITORING | |
|
From: SR 46
To: WEST SIDE OF BRISSON AVE
Scope: PART 1. DESIGN OF A REGIONAL STORMWATER FACILITY ADDRESSING FLOOD ATTENUATION AND WATER QUALITY TREATMENT. THE PROJECT IS THE CONVERSION OF OVER 100 ACRES OF AN EXISTING BORROW PIT TO A REGIONAL STORMWATER FACILITY LOCATED WEST OF BRISSON AVENUE AND SOUTH OF FIRST DRIVE. PART 2. CONCRETE PILING CLEAN UP. PART 3. WATER QUALITY MONITORING. FLORIDA DEPARTMENT OF ENVIRONMENTAL PROTECTION AGREEMENT # S0163 Phases:
Design Start: 7/2005 End: 5/2006
Construction Start: 1/2007 End: 5/2007 Road Construction Start: End: |
||||
| CONTINENTAL BLVD AT COUNTRY CLUB HEIGHTS SUBDIVISION RETROFIT | SUBDIVISION REHABILITATION PROJECTS | Mark Flomerfelt
mflomerfelt@seminolecountyfl.gov 407-665-5709 |
ACTIVE | |
|
From: COUNTRY CLUB RD
To: CLYDE AVE
Scope: DRAINAGE WORK FOR COUNTRY CLUB HEIGHTS SUBDIVISION FROM COUNTRY CLUB RD TO CLYDE AVE. Phases:
Construction Start: 12/2009 End: 2/2010
|
||||
| COUNTRY CLUB OR C-15 SIDEWALK | SIDEWALK PROJECTS | Eric Erickson
eerickson@seminolecountyfl.gov 407-665-5666 |
ACTIVE | |
|
From: FREDERICK AVE
To: ALMA AVE
Scope: THIS PROJECT WILL CONSTRUCT APPROXIMATELY 1,000 LINEAR FEET OF SIDEWALK ON THE WEST SIDE OF COUNTRY CLUB RD FROM FREDERICK AVE TO ALMA AVE. Phases:
Construction Start: 4/2010 End: 6/2010
|
||||
| COUNTRY CLUB RD ROADWAY REBUILD | MINOR PROJECTS ROAD PROGRAM | Ken Mickenberg
kmickenberg@seminolecountyfl.gov 407-665-5714 |
ACTIVE | |
|
From: RANTOUL LN
To: CR 46A
Scope: THIS PROJECT WILL REBUILD THE ROADWAY WITH DRAINAGE IMPROVEMENTS. THE PROJECT LENGTH IS APPROXIMATELY 1.3 MILES Phases:
Design Start: 3/2008 End: 12/2008
Road Construction Start: 6/2009 End: 10/2009 |
||||
| COUNTY RD 46A SIDEWALK | SIDEWALK PROJECTS | Eric Erickson
eerickson@seminolecountyfl.gov 407-665-5666 |
ACTIVE | |
|
From: RIDGEWOOD AVE.
To: US HWY 17-92
Scope: THIS PROJECT WILL CONSTRUCT 2,600 LINEAR FEET OF SIDEWALK ON THE SOUTH SIDE OF C.R. 46-A FROM THE SEMINOLE ANIMAL HOSPITAL TO OLD LAKE MARY ROAD AND FROM 400` WEST OF RIDGEWOOD AVENUE TO THE CITY OF SANFORD PARK Phases:
Design Start: 1/2009 End: 12/2009
Land Start: 5/2008 End: 12/2009 Construction Start: 10/2009 End: 11/2009 |
||||
| COURTLAND LOOP CONSTRUCTION AT TUSKA BAY SUBDIVISION RETROFIT | SUBDIVISION REHABILITATION PROJECTS | Mark Flomerfelt
mflomerfelt@seminolecountyfl.gov 407-665-5709 |
ACTIVE | |
|
From: TUSKAWILLA RD
To: TUSKAWILLA RD
Scope: DRAINAGE IMPROVEMENTS FOR TUSKA BAY SUBDIVISION FROM TUSKAWILLA RD TO TUSKAWILLA RD. Phases:
Construction Start: 1/2009 End: 12/2009
|
||||
| CR 15 WIDEN FROM 2 TO 5 LANES WITH BIDIRECTIONAL LANE | MAJOR ROAD PROGRAM | Brett Blackadar
BBlackadar@seminolecountyfl.gov 407-665-5702 |
ACTIVE | |
|
From: SR 46
To: ORANGE BLVD
Scope: THE PROJECT WILL WIDEN THE ROADWAY FROM 2 TO 5 LANES WITH A BI-DIRECTIONAL CENTER TURN LANE. THE PROJECT LENGTH IS 1.2 MILES. FLORIDA DEPARTMENT OF TRANSPORTATION AGREEMENT # AO977 BCC DATE 12/20/05, BCC ACTION # 48 FUNDING AGREEMENT BCC DATE 09/11/07, BCC ACTION # 26, AMENDMENT I Phases:
Design Start: 12/1999 End: 6/2007
Land Start: 2/2003 End: 12/2009 Construction Start: 1/2008 End: 7/2009 Road Construction Start: 1/2008 End: 7/2009 |
||||
| CR 419 WIDENING LANES | MAJOR ROAD PROGRAM | Brett Blackadar
BBlackadar@seminolecountyfl.gov 407-665-5702 |
ACTIVE | |
|
From: SNOWHILL RD
To: ORANGE COUNTY LINE
Scope: THIS PROJECT WILL WIDEN THE ROADWAY FROM TWO TO FOUR LANES. THE APPROXIMATE PROJECT LENGTH IS 2.6 MILES. FOR MORE INFORMATION, PLEASE VISIT HTTP://WWW.PECONLINE.COM/SEMINOLE/ Phases:
Design Start: 4/2009 End: 4/2010
Land Start: 7/2010 End: 12/2011 Road Construction Start: 4/2012 End: 4/2014 |
||||
| CR 426 SAFETY IMPROVEMENTS | MINOR PROJECTS ROAD PROGRAM | Shad Smith
ssmith@seminolecountyfl.gov 407-665-5707 |
ACTIVE | |
|
From: DIVISION ST
To: SR 46
Scope: THIS PROJECT CONSISTS OF ENGINEERING DESIGN OF SAFETY IMPROVEMENTS WHICH, WILL INCLUDE ADDING PAVED SHOULDERS AND ENHANCING OTHER SAFETY ITEMS. THE PROJECT INCLUDES RIGHT OF WAY TO ADD IMPROVEMENTS. FLORIDA DEPARTMENT OF TRANSPORTATION SAFETY FUNDS ARE BEING UTILIZED. FLORIDA DEPARTMENT OF TRANSPORTATION AGREEMENT # AOV36 FLORIDA DEPARTMENT OF TRANSPORTATION ADDITIONAL ANTICIPATED AGREEMENT Phases:
Design Start: 3/2006 End: 4/2010
Land Start: 8/2009 End: 8/2010 Road Construction Start: 2/2011 End: 2/2012 |
||||
| CR 427 AND NORTH ST INTERSECTION IMPROVEMENTS | MINOR PROJECTS ROAD PROGRAM | ACTIVE | ||
|
From: INTERSECTION
To: INTERSECTION
Scope: ADDITION OF A SOUTHBOUND RIGHT TURN LANE. Phases:
Design Start: 10/2009 End: 9/2010
Land Start: 10/2009 End: 9/2010 |
||||
| CR 427 FIBER OPTIC UPGRADE | TRAFFIC FIBER OPTIC AND ATMS NETWORK | Charles Wetzel Iii | ACTIVE | |
|
From: US 17-92
To: LAKE MARY BLVD
Scope: UPGRADE OF EXISTING FIBER FOR INCREASED CAPACITY. Phases:
Road Construction Start: 2/2009 End: 9/2009
|
||||
| CR 431 AT ORANGE BLVD DRAINAGE IMPROVEMENTS | MINOR PROJECTS ROAD PROGRAM | Eric Erickson
eerickson@seminolecountyfl.gov 407-665-5666 |
ACTIVE | |
|
From: CR 46A
To: SR 46
Scope: CREATE A THREE LANE SECTION WITH A BI-DIRECTIONAL TURN LANE AND IMPROVE DRAINAGE. THE PROJECT LENGTH IS 1.7 MILES Phases:
Design Start: 3/2004 End: 10/2010
Road Construction Start: 5/2008 End: 10/2009 |
||||
| CR 46A AT COLONIAL PKWY INTERSECTION IMPROVEMENTS | MINOR PROJECTS ROAD PROGRAM | Brett Blackadar
BBlackadar@seminolecountyfl.gov 407-665-5702 |
ACTIVE | |
|
From: INTERSECTION
To: INTERSECTION
Scope: THIS PROJECT WILL ADD A WESTBOUND RIGHT TURN LANE TO THE INTERSECTION. Phases:
Design Start: 1/2008 End: 12/2008
Road Construction Start: 1/2009 End: 3/2009 |
||||
| CR 46A WALLS & LANDSCAPING | MAJOR ROAD PROGRAM | David Andrews, Jr.
dandrews@seminolecountyfl.gov 407-665-5716 |
ACTIVE | |
|
From: CR 15
To: OLD LAKE MARY RD
Scope: THIS PROJECT WILL BUILD A SIX FOOT HIGH WALL FOR LOCH ARBOR SUBDIVISION AND TWO PRIVACY WALLS LOCATED ON CR 46A. THE PROJECT WILL ALSO INCLUDE TREE REMOVAL FOR LOCH ARBOR SUBDIVISION WALL, LANDSCAPING OF POND, AND LANDSCAPING ALONG THE CR 46A ROADWAY. Phases:
Road Construction Start: 7/2009 End: 12/2009
|
||||
| CROSS SEMINOLE TRL PH III | TRAILS | David Martin
dmartin02@seminolecountyfl.gov 407-665-5610 |
CLOSEOUT TRANSITION | |
|
From: SR 426
To: SR 434
Scope: CONSTRUCTION OF APPROXIMATELY 1.0 MILES OF TRAIL, 6 TO 8 FOOT WIDE UNPAVED PATH AND .75 MILES OF WETLAND RESTORATION FROM SR 426 TO SR 434. FLORIDA DEPARTMENT OF TRANSPORTAION AGREEMENT # 413747-1-58-01 Phases:
Construction Start: 6/2008 End: 5/2009
Road Construction Start: 6/2008 End: 5/2009 |
||||
| CROSS SEMINOLE TRL SOUTH II | TRAILS | David Martin
dmartin02@seminolecountyfl.gov 407-665-5610 |
CLOSEOUT TRANSITION | |
|
From: MIKLER ROAD
To: RED BUG LAKE RD
Scope: CONSTRUCTION OF APPROXIMATELY 1.8 MILES OF 14 FOOT WIDE TRAIL WITHIN FLORIDA DEPARTMENT OF TRANSPORTATION`S SR 426 RIGHT OF WAY. FLORIDA DEPARTMENT OF TRANSPORTATION AGREEMENT # AP360 Phases:
Construction Start: 8/2008 End: 5/2009
|
||||
| DEAN RD WIDEN FROM 2 TO 4 LANES | MAJOR ROAD PROGRAM | Brett Blackadar
BBlackadar@seminolecountyfl.gov 407-665-5702 |
ACTIVE | |
|
From: SR 426
To: ORANGE COUNTY LINE
Scope: THIS PROJECT WILL WIDEN THE ROADWAY FROM 2 TO 4 LANES. THE APPROXIMATE LENGTH IS 0.6 MILES Phases:
Design Start: 11/2009 End: 12/2011
Land Start: 10/2010 End: 9/2011 Road Construction Start: 10/2012 End: 9/2013 |
||||
| DODD RD DETECTABLE WARNINGS | TRAFFIC SAFETY/RAILROAD CROSSING | Melonie Barrington
mbarrington@seminolecountyfl.gov 407-665-5676 |
ACTIVE | |
|
From: EAGLE BLVD
To: HOWELL BRANCH RD
Scope: INSTALL DETECTABLE WARNINGS. RECONSTRUCT 2 RAMPS AND INSTALL 31 TRUNCATED DOMES FOR ADA COMPLIANCE. Phases:
Road Construction Start: 6/2009 End: 9/2009
|
||||
| DYSON DR SIDEWALK PH 1 | SCHOOL SAFETY RELATED SIDEWALK PROJECTS | David Andrews, Jr.
dandrews@seminolecountyfl.gov 407-665-5716 |
ACTIVE | |
|
From: TUSKAWILLA RD
To: SHETLAND RD
Scope: THIS PROJECT WILL CONSTRUCT APPROXIMATELY 3,100 LINEAR FEET OF SIDEWALK ON BOTH SIDES OF DYSON DRIVE FROM TUSKAWILLA ROAD TO HOWELL CREEK. THE PROJECT INCLUDES DRAINAGE IMPROVEMENTS AND A NEW PEDESTRIAN BRIDGE OVER HOWELL CREEK. Phases:
Design Start: 6/2004 End: 3/2009
Construction Start: 6/2009 End: 10/2009 |
||||
| DYSON DR SIDEWALK PH 2 | SIDEWALK PROJECTS | David Andrews, Jr.
dandrews@seminolecountyfl.gov 407-665-5716 |
ACTIVE | |
|
From: TUSKAWILLA RD
To: HOWELL CREEK BRIDGE
Scope: THIS PROJECT WILL CONSTRUCT APPROXIMATELY 3,100 LINEAR FEET OF SIDEWALK ON BOTH SIDES OF DYSON DR FROM TUSKAWILLA RD TO HOWELL CREEK. THE PROJECT INCLUDES DRAINAGE IMPROVEMENTS AND A NEW PEDESTRIAN BRIDGE OVER HOWELL CREEK. Phases:
Construction Start: 6/2009 End: 10/2009
|
||||
| E LAKE MARY BLVD SIGNAGE | MAJOR ROAD PROGRAM | David Andrews, Jr.
dandrews@seminolecountyfl.gov 407-665-5716 |
ACTIVE | |
|
From: AIRPORT ENTRANCE RD
To: SR 46
Scope: THIS PROJECT WILL DESIGN AND CONSTRUCT DIRECTIONAL SIGNAGE FOR AIRPORT ENTRANCE ON E LAKE MARY BLVD. THIS PROJECT IS RELATED TO CIP #010701 AND #010704. Phases:
Design Start: 10/2008 End: 10/2008
Road Construction Start: 8/2009 End: 3/2010 |
||||
| EAGLE CIR AT DEER RUN SUBDIVISION RETROFIT | SUBDIVISION REHABILITATION PROJECTS | Rolando Raymundo
RRaymundo@seminolecountyfl.gov 407-665-5715 |
ACTIVE | |
|
From: RED BUG LAKE RD
To: EAGLE CIR
Scope: PIPELINING FOR DEER RUN SUBDIVISION FROM RED BUD LAKE RD TO EAGLE CIR. Phases:
Construction Start: 12/2009 End: 2/2010
|
||||
| ELDER CREEK AND ELDER RD SALES TAX CR 15 POND IMPROVEMENTS | PRIMARY SYSTEM STORMWATER PROJECT (SALES TAX) | Robert Walter
RWalter@seminolecountyfl.gov 407-665-5753 |
ACTIVE | |
|
From: NARCISSUS AVE
To: CHURCH ST
Scope: PART 1. DESIGN AND CONSTRUCTION OF A REGIONAL STORMWATER POND ADDRESSING AREA FLOODING, PROVIDING WATER QUALITY TREATMENT, AND SERVING A SEGMENT OF CR 15. PART 2. ADDITIONAL 600 LINEAR FEET OF ROADWAY TO BE CONSTRUCTED. FLORIDA DEPARTMENT OF ENVIORNMENTAL PROTECTION AGREEMENT # S0341 BCC DATE 08/28/07, ACTION # 38, FUNDING AGREEMENT Phases:
Design Start: 1/2001 End: 6/2008
Land Start: 10/2003 End: 3/2006 Construction Start: 11/2007 End: 2/2008 |
||||
| FERNWOOD BLVD PEDESTRIAN CROSSING LOCAL AGENCY PARTICIPATION | SIDEWALK PROJECTS | David Martin
dmartin02@seminolecountyfl.gov 407-665-5610 |
ACTIVE | |
|
From: AT LYNX BUS STOP
To: AT LYNX BUS STOP
Scope: THIS PROJECT WILL DESIGN A RAISED PEDESTRIAN CROSSING 22 FEET IN WIDTH ACROSS THE EAST AND WEST BOUND LANES OF TRAFFIC ON FERNWOOD BLVD. THIS CROSSING WILL BE A SMOOTH UNIFORM, NON-SKID SURFACE OF CONTRASTING COLOR WITH 10` WIDE HIGH EMPHASIS CROSSWALK MARKING WITHIN THE CENTER 10 FEET OF THE CROSSING. FLORIDA DEPARTMENT OF TRANSPORTATION AGREEMENT # APB 77 Phases:
Design Start: 3/2007 End: 9/2007
Road Construction Start: End: |
||||
| GREENWOOD BLVD SIDEWALK | SIDEWALK PROJECTS | David Andrews, Jr.
dandrews@seminolecountyfl.gov 407-665-5716 |
ACTIVE | |
|
From: LAKE EMMA ROAD
To: HEATHER DOWN LANE
Scope: CONSTRUCT SIDEWALK ON NORTH SIDE OF GREENWOOD BLVD. FROM LAKE EMMA RD TO 150` EAST OF PEBBLE CREEK CIRCLE & REPAIR EXISTING SIDEWALK FROM 150` EAST OF PEBBLE CREEK CIRCLE TO HEATHER DOWN LANE. Phases:
Land Start: 10/2008 End: 10/2009
Construction Start: 1/2010 End: 3/2010 |
||||
| HOWELL BRANCH RD DETECTABLE WARNINGS | TRAFFIC SAFETY/RAILROAD CROSSING | Melonie Barrington
mbarrington@seminolecountyfl.gov 407-665-5676 |
ACTIVE | |
|
From: SR 426
To: W TO COUNTY LINE
Scope: DETECTABLE WARNINGS. RECONSTRUCT 2 RAMPS AND INSTALL 31 TRUNCATED DOMES FOR ADA COMPLIANCE. Phases:
Road Construction Start: 6/2009 End: 9/2009
|
||||
| HOWELL BRANCH RD LANDSCAPING | MAJOR ROAD PROGRAM - SPECIAL PROJECTS | David Martin
dmartin02@seminolecountyfl.gov 407-665-5610 |
ACTIVE | |
|
From: LAKE HOWELL RD
To: SR 436
Scope: ADD LANDSCAPING TO ROADWAY PARCEL Phases:
Road Construction Start: End:
|
||||
| HOWELL CREEK DAM AT LAKE HOWELL RD WATER CONTROL STRUCTURE | PRIMARY SYSTEM STORMWATER PROJECT | Rolando Raymundo
RRaymundo@seminolecountyfl.gov 407-665-5715 |
ACTIVE | |
|
From: ORANGE COUNTY LINE
To: LAKE HOWELL RD
Scope: REPLACE EXISTING RUBBLE DAM WEST OF LAKE HOWELL RD. NATURAL RESOURCES CONSERVATION SERVICE (NRCS) AGREEMENT # 64-4209-9-1722 Phases:
Design Start: 12/2008 End: 12/2009
Construction Start: 4/2009 End: 7/2009 Road Construction Start: 4/2009 End: 12/2009 |
||||
| HUNT CLUB AT E WEKIVA TRL MAST ARMS | TRAFFIC SIGNALS | Charles Wetzel Iii | ACTIVE | |
|
From: N/A
To: N/A
Scope: CONVERSION OF AN EXISTING SPAN WIRE SIGNAL TO MAST ARMS. Phases:
Road Construction Start: 1/2009 End: 8/2009
|
||||
| HUNT LN AT FOX RUN SUBDIVSION RETROFIT | SUBDIVISION REHABILITATION PROJECTS | Rolando Raymundo
RRaymundo@seminolecountyfl.gov 407-665-5715 |
ACTIVE | |
|
From: PARK RD
To: FOX ROW AVE
Scope: DRAINAGE IMPROVEMENTS FOR FOX RUN SUBDIVISION FROM PARK RD TO FOX ROW AVE. Phases:
Construction Start: 12/2009 End: 2/2010
|
||||
| IFAS MIDWAY REGIONAL STORMWATER FACILITY JOINT PARTICIPATION PROJECT | PRIMARY SYSTEM STORMWATER PROJECT (JPP) | Robert Walter
RWalter@seminolecountyfl.gov 407-665-5753 |
ACTIVE | |
|
From: CELERY AVE
To: SIPES AVE
Scope: DESIGN AND CONSTRUCTION OF A REGIONAL STORMWATER FACILITY PROVIDING FLOOD ATTENUATION AND WATER QUALITY TREATMENT FOR THE MIDWAY AREA. ALSO COMBINED WITH FLORIDA DEPARTMENT OF TRANSPORATION PROJECT SR 415. ST JOHNS RIVER WATER MANAGEMENT DISTRICT AGREEMENT # SJ456AA ST JOHNS RIVER WATER MANAGEMENT DISTRICT AGREEMENT # SI433AA FLORIDA DEPARTMENT OF TRANSPORTATION AGREEMENT # AP459 Phases:
Construction Start: 1/2009 End: 10/2009
|
||||
| IRON GATE CT AT MIDDLETON OAKS ASPHALT SURFACE AND PAVEMENT MANAGEMENT | RESURFACING | Harry Raysin
hraysin@seminolecountyfl.gov 407-665-2839 |
ACTIVE | |
|
From: OLD MAIL LN
To: CUL DE SAC
Scope: ASPHALT OVERLAY, FULL DEPTH RECLAMATION, AND VARIOUS METHODS OF ASPHALT SURFACE REFURBISHMENT THAT ARE APPLIED TO SEMINOLE COUNTY’S PAVED ROAD NETWORK. THIS INCLUDES LOCAL ROAD RESURFACING AND REHABILITATION THAT MAY INVOLVE RECONSTRUCTION ACTIVITY. THIS ALSO INCLUDES RESURFACING OF ARTERIAL/COLLECTOR ROADS NOT INVOLVING THE ROADWAY BASE. Phases:
Construction Start: 10/2009 End: 9/2010
|
||||
| JAMESTOWN COMMUNITY SIDEWALK | SIDEWALK PROJECTS | Ken Mickenberg
kmickenberg@seminolecountyfl.gov 407-665-5714 |
ACTIVE | |
|
From: VARIOUS LOCATIONS
To: VARIOUS LOCATIONS
Scope: THIS PROJECT WILL ADD SIDEWALKS TO THE JAMESTOWN COMMUNITY. THE LOCATIONS OF THE SIDEWALKS WILL BE DETERMINED AS PART OF THE DESIGN PROGRAMMED IN FY 2009/2010. Phases:
Design Start: 4/2009 End: 12/2009
Construction Start: 1/2010 End: 4/2010 |
||||
| LAKE EMMA RD WIDEN FROM 2 TO 4 LANES | MAJOR ROAD PROGRAM | David Andrews, Jr.
dandrews@seminolecountyfl.gov 407-665-5716 |
ACTIVE | |
|
From: SAND POND RD
To: LONGWOOD HILLS RD
Scope: THE ROADWAY WILL BE WIDENED FROM 2 TO 4 LANES. THE APPROXIMATE PROJECT LENGTH IS 2.0 MILES Phases:
Design Start: 5/1996 End: 4/2009
Land Start: 2/2001 End: 6/2008 Road Construction Start: 11/2009 End: 12/2010 |
||||
| LAKE HOWELL HIGH SCHOOL TRAFFIC CIRCULATION FEASIBILITY STUDY | SCHOOL TRAFFIC CIRCULATION | Melonie Barrington
mbarrington@seminolecountyfl.gov 407-665-5676 |
ACTIVE | |
|
Scope: THIS INTIAL PHASE OF THE PROJECT IS A FEASIBILITY STUDY DETERMINING WHICH OF THE FOLLOWING OPTIONS WOULD BEST IMPROVE TRAFFIC CIRCULATION AT THE SCHOOL;
-ADDITIONAL DRIVEWAY CONNECTION TO DIKE RD.(INCLUDING PROVISION FOR RIGHT TURN LANE).
-RECONFIGURATION OF PARKING AT THE DRIVER EDUCATION AREA
-STUDY OF EXISTION MAIN CAMPUS DRIVEWAY CONNECTION TO DIKE RD.
-RECONFIGURATION OF ON SITE DRIVEWAYS AND PARKING AREAS
THE REMAINING FUNDS WOULD PARTIALLY FUND WHICHEVER ALTERNATIVE IS SELECTED.
Phases:
Design Start: End:
Road Construction Start: End: |
||||
| LAKE HOWELL RD PH 2 PAVEMENT REHABILITATION | ARTERIAL/COLLECTOR PAVEMENT REHABILITATION | Harry Raysin
hraysin@seminolecountyfl.gov 407-665-2839 |
ACTIVE | |
|
From: ORANGE COUNTY LINE
To: HOWELL BRANCH RD
Scope: ASPHALT OVERLAY, FULL DEPTH RECLAMATION, AND/OR VARIOUS REHABILITATION METHODS. (I.E. PIPE LINING OR REPLACEMENT, MILL AND RESURFACE). (COLLECTOR) Phases:
Construction Start: 6/2009 End: 9/2009
|
||||
| LAKE JESUP BASIN RSF (NAVY CANAL/SJRWMD MITIGATION) | PRIMARY SYSTEM STORMWATER PROJECT (JPP) | Robert Walter
RWalter@seminolecountyfl.gov 407-665-5753 |
MONITORING | |
|
From: E LAKE MARY BLVD
To: SOUTH OF SAND DOLLAR PT
Scope: THIS PROJECT WILL MITIGATE THE CONSTRUCTION OF REGIONAL STORMWATER FACILITY FOR FLOOD ATTENUATION AND WATER QUALITY TREATMENT. FLORIDA DEPARTMENT OF ENVIORNMENTAL PROTECTION AGREEMENT # S0341 BCC DATE 08/28/07, ACTION # 38, FUNDING AGREEMENT Phases:
Design Start: 3/2003 End: 11/2006
Land Start: 10/2003 End: 9/2004 Construction Start: 4/2006 End: 11/2007 |
||||
| LAKE JESUP TMDL PROJECT - HOWELL CREEK ALUM PROJECT | WATER QUALITY/TMDL`s | Kimberly Ornberg
kornberg@seminolecountyfl.gov 407-665-5738 |
ACTIVE | |
|
Scope: PROJECT IS A REGIONAL STORMWATER FACILITY (RSF) TO REMOVE PHOSPHORUS FROM HOWELL CREEK, ULTIMATELY LAKE HOWELL AND LAKE JESUP.
Phases:
Design Start: 10/2011 End: 9/2012
Land Start: 10/2010 End: 9/2011 Construction Start: 10/2012 End: 9/2013 |
||||
| LAKE JESUP TMDL PROJECT - SOLDIERS CREEK AT CR 427 RSF | PRIMARY SYSTEM STORMWATER PROJECT | Mark Flomerfelt
mflomerfelt@seminolecountyfl.gov 407-665-5709 |
ACTIVE | |
|
Scope: PROJECT IS A REGIONAL STORMWATER FACILITY (RSF) TO REMOVE PHOSPHORUS FROM SOLDIERS CREEK, ULTIMATELY LAKE JESUP.
Phases:
Design Start: 11/2009 End: 9/2010
Construction Start: 1/2011 End: 9/2011 |
||||
| LAKE MARY BLVD AT INTERNATIONAL PKWY PEDESTRIAN OVERPASS | PEDESTRIAN OVERPASSES / UNDERPASSES | David Martin
dmartin02@seminolecountyfl.gov 407-665-5610 |
ACTIVE | |
|
From: N/A
To: N/A
Scope: CONSTRUCT A PEDESTRIAN UNDERPASS TO CROSS PEDESTRIANS SAFELY PAST THE INTERSECTION OF LAKE MARY BLVD AT INTERNATIONAL PKWY. DESIGN IS UNDERWAY. Phases:
Design Start: 2/2006 End: 12/2009
Construction Start: 1/2010 End: 6/2011 |
||||
| LAKE MARY BLVD AT SUN DR SECONDARY DRAINAGE | SECONDARY SYSTEM STORMWATER PROJECT (SALES TAX) | Rolando Raymundo
RRaymundo@seminolecountyfl.gov 407-665-5715 |
ACTIVE | |
|
From: RINEHART RD
To: LAKE EMMA RD
Scope: PRELIMINARY ENGINEERING DESIGN FOR SECONDARY DRAINAGE ON LAKE MARY BLVD AND OUTFALL ALONG SUN DR. Phases:
Design Start: 12/2008 End: 10/2010
Construction Start: 11/2010 End: 10/2011 |
||||
| LAKE MARY BLVD AT US 17-92 INTERSECTION IMPROVEMENTS | MINOR PROJECTS ROAD PROGRAM | Ken Mickenberg
kmickenberg@seminolecountyfl.gov 407-665-5714 |
CLOSEOUT TRANSITION | |
|
From: INTERSECTION
To: INTERSECTION
Scope: THIS PROJECT WILL ADD A RIGHT TURN LANE TO THE INTERSECTION ON LAKE MARY BLVD ONTO NORTHBOUND US 17-92. Phases:
Design Start: 11/2007 End: 1/2009
Road Construction Start: 5/2009 End: 8/2009 |
||||
| LINCOLN HEIGHTS DRAINAGE IMPROVEMENTS | SECONDARY SYSTEM STORMWATER PROJECT (SALES TAX) | Robert Walter
RWalter@seminolecountyfl.gov 407-665-5753 |
ACTIVE | |
|
From: AIRPORT BLVD
To: LINCOLN AVE
Scope: MAJOR FLOOD ATTENUATION PROJECT ADDRESSING THE CHRONIC FLOODING OF THE LINCOLN HEIGHTS SUBDIVISION. Phases:
Design Start: 9/2007 End: 12/2009
Land Start: 1/2007 End: 11/2009 Construction Start: 1/2010 End: 12/2010 |
||||
| LOCKHART SMITH REGIONAL FACILITY | PRIMARY SYSTEM STORMWATER PROJECT (JPP) | Rolando Raymundo
RRaymundo@seminolecountyfl.gov 407-665-5715 |
ACTIVE | |
|
From: 500` W OF INTERSTATE 4
To: 1/2 MILE NORTH OF SR 46
Scope: CONSTRUCTION OF REGIONAL STORMWATER POND AT SITE FORMALLY KNOWN AS I-4 BORROW PIT. FLORIDA DEPARTMENT OF TRANSPORTATION AGREEMENT # S0261 Phases:
Construction Start: 1/2007 End: 9/2007
|
||||
| LOCKWOOD BLVD DETECTABLE WARNINGS | TRAFFIC SAFETY/RAILROAD CROSSING | Melonie Barrington
mbarrington@seminolecountyfl.gov 407-665-5676 |
ACTIVE | |
|
From: MCCULLOCH RD
To: SOUTH TO END OF COUNTY MAINTAINED ROADWAY
Scope: DETECTABLE WARNINGS. RECONSTRUCT 14 RAMPS AND INSTALL 50 TRUNCATED DOMES FOR ADA COMPLIANCE. Phases:
Road Construction Start: 6/2009 End: 9/2009
|
||||
| LONGWOOD LAKE MARY RD CENTER TURN LANE | MINOR PROJECTS ROAD PROGRAM | Harry Raysin
hraysin@seminolecountyfl.gov 407-665-2839 |
ACTIVE | |
|
From: LAKE PARK RD
To: GREENWAY BLVD
Scope: THIS PROJECT WILL RECONSTRUCT THE ROADWAY TO IMPROVE THE PAVEMENT CONDITION. A PORTION OF THE ROADWAY BETWEEN LAKE PARK DR AND LAKE MARY HIGH SCHOOL WAS COMPLETED IN DECEMBER 2008. Phases:
Design Start: 2/2008 End: 9/2008
Land Start: 6/2009 End: 7/2010 Road Construction Start: 12/2009 End: 11/2010 |
||||
| LONGWOOD-MARKHAM RD/ MARKHAM RD SIDEWALK | SIDEWALK PROJECTS | Ken Mickenberg
kmickenberg@seminolecountyfl.gov 407-665-5714 |
ACTIVE | |
|
From: RAMBLING RIVER DR
To: MARKHAM RD TRAILHEAD
Scope: THIS PROJECT WILL CONSTRUCT 760 LINEAR FEET OF SIDEWALK ON WEST SIDE OF LONGWOOD MARKHAM RD, SOUTH FROM RAMBLING RIVER DR AND 2,670` LINEAR FEET OF SIDEWALK ON THE EAST SIDE OF LONGWOOD MARKHAM RD EAST TO THE MARKHAM ROAD TRAILHEAD WITHIN THE RAILROAD RIGHT OF WAY ON THE NORTH SIDE OF MARKHAM RD. Phases:
Design Start: 4/2008 End: 1/2010
Construction Start: 3/2010 End: 7/2010 |
||||
| MAGNOLIA AVE UNPAVED ROADS | UNPAVED ROADS | Jimmie Beach, Jr.
jbeach@seminolecountyfl.gov 407-665-5606 |
ACTIVE | |
|
From: 27TH ST
To: SOUTH TO PAVEMENT
Scope: PROJECT LENGTH IS 0.26 MILES. WORK ASSOCIATED WITH THE APPLICATION OF AN ALTERNATIVE SURFACE TREATMENT (DRAINAGE IMPROVEMENTS, BASE RECONSTRUCTION, AND ASPHALT PAVING) Phases:
Land Start: 7/2006 End: 4/2008
Road Construction Start: 7/2008 End: 9/2009 |
||||
| MAITLAND AVE DETECTABLE WARNINGS | TRAFFIC SAFETY/RAILROAD CROSSING | Melonie Barrington
mbarrington@seminolecountyfl.gov 407-665-5676 |
ACTIVE | |
|
From: SR 436
To: SOUTH TO COUNTY LINE
Scope: DETECTABLE WARNINGS. RECONSTRUCT 7 RAMPS AND INSTALL TRUNCATED DOMES FOR ADA COMPLIANCE. Phases:
Road Construction Start: 6/2009 End: 9/2009
|
||||
| MARKHAM WOOD GRAVITY WALL | UNIQUE MAJOR PROJECTS | Mike Van Der Heyden
mvanderheyden@seminolecountyfl.gov 407-665-5748 |
ACTIVE | |
|
From: NA
To: NA
Scope: THIS PROJECT WILL REPAIR GRAVITY WALL ON MARKHAM WOODS RD. Phases:
Construction Start: 6/2009 End: 7/2009
|
||||
| MARKHAM WOODS RD ADD CENTER LANE PH 1 | MINOR PROJECTS ROAD PROGRAM | Brett Blackadar
BBlackadar@seminolecountyfl.gov 407-665-5702 |
ACTIVE | |
|
From: EE WILLIAMSON RD
To: MARKHAM RD
Scope: THIS PROJECT WILL ADD LEFT TURN LANES AT 7 LOCATIONS AND WILL EXTEND THE EXISTING LEFT TURN LANE AT EE WILLIAMSON RD. THIS PROJECT WILL ALSO IMPROVE THE EXISTING PAVEMENT FOR THE SECTION NORTH OF LAKE MARY BLVD. THE PROJECT LENGTH IS APPROXIMATELY 5.0 MILES. Phases:
Design Start: 2/2007 End: 1/2009
Land Start: 10/2007 End: 9/2008 Road Construction Start: 5/2009 End: 10/2009 |
||||
| MCCULLOCH RD DETECTABLE WARNINGS | TRAFFIC SAFETY/RAILROAD CROSSING | Melonie Barrington
mbarrington@seminolecountyfl.gov 407-665-5676 |
ACTIVE | |
|
From: SR 434
To: LOCKWOOD BLVD
Scope: DETECTABLE WARNINGS. RECONSTRUCT 1 RAMP AND INSTALL 30 TRUNCATED DOMES FOR ADA COMPLIANCE. Phases:
Road Construction Start: 6/2009 End: 9/2009
|
||||
| MIDWAY ELEMENTARY SCHOOL SIDEWALK | SIDEWALK PROJECTS | Ken Mickenberg
kmickenberg@seminolecountyfl.gov 407-665-5714 |
ACTIVE | |
|
From: MIDWAY ELEMENTARY SCHOOL
To: SURROUNDING AREAS
Scope: CONSTRUCT 11,850 LINEAR FEET OF SIDEWALKS TO CONNECT TO NEW MIDWAY ELEMENTARY SCHOOL. INCLUDES 4000 LF ON BRISSON AVE. 1650 LF ON KINGS RD. 1300 LF ON CRAWFORD DR. 1300 LF ON BYRD AVE. 1100 LF ON GRANBY ST. 1000 LF ON E. 20TH STREET. 650 LF ON RUFF RD. 500 LF ON JITWAY AVE. 350 LF ON LINGARD AVE. Phases:
Design Start: 4/2009 End: 1/2010
Construction Start: 3/2010 End: 6/2010 |
||||
| MIDWAY REGIONAL STORMWATER FACILITY DEMOLITION | PRIMARY SYSTEM STORMWATER PROJECT (JPP) | Robert Walter
RWalter@seminolecountyfl.gov 407-665-5753 |
ACTIVE | |
|
From: CELERY AVE
To: SIPES AVE
Scope: DEMOLITION IN PREPARATION OF DESIGN OF A REGIONAL STORMWATER FACILITY PROVIDING FLOOD ATTENUATION AND WATER QUALITY TREATMENT FOR THE MIDWAY AREA. SAINT JOHNS RIVER WATER MANAGEMENT AGREEMENT # SJ456AA BCC DATE 06/27/06, ACTION # 34, FUNDING AGREEMENT Phases:
Land Start: 3/2007 End: 5/2010
Construction Start: 2/2007 End: 5/2010 |
||||
| MIKLER RD SIDEWALK | SIDEWALK PROJECTS | Ken Mickenberg
kmickenberg@seminolecountyfl.gov 407-665-5714 |
ACTIVE | |
|
From: RED BUG LAKE RD
To: MORNING STAR PL
Scope: THIS PROJECT WILL CONSTRUCT MISSING GAPS ON APPROXIMATELY 2,700 LINEAR FEET ON MIKLER RD BETWEEN RED BUG LAKE RD AND MORNING STAR PL. Phases:
Design Start: 3/2009 End: 10/2009
Construction Start: 1/2010 End: 3/2010 |
||||
| NORTH ST PAVEMENT REHABILITATION | ARTERIAL/COLLECTOR PAVEMENT REHABILITATION | ACTIVE | ||
|
From: COUNTRY CLUB RD
To: SEMINOLE AVE
Scope: ASPHALT OVERLAY, FULL DEPTH RECLAMATION, AND/OR VARIOUS REHABILITATION METHODS. (I.E. PIPE LINING OR REPLACEMENT, MILL AND RESURFACE). (COLLECTOR). Phases:
Construction Start: 3/2009 End: 6/2009
|
||||
| OLD LAKE MARY RD PAVEMENT REHABILITATION PH 1 | ARTERIAL/COLLECTOR PAVEMENT REHABILITATION | Harry Raysin
hraysin@seminolecountyfl.gov 407-665-2839 |
ACTIVE | |
|
From: N PALMETTO ST
To: AIRPORT BLVD
Scope: ASPHALT OVERLAY, FULL DEPTH RECLAMATION, AND/OR VARIOUS REHABILITATION METHODS. (I.E. PIPE LINING OR REPLACEMENT, MILL AND RESURFACE). (COLLECTOR) Phases:
Construction Start: 4/2009 End: 6/2009
|
||||
| OLD MAIL LN AT MIDDLETON OAKS ASPHALT SURFACE AND PAVEMENT MANAGEMENT | RESURFACING | Harry Raysin
hraysin@seminolecountyfl.gov 407-665-2839 |
ACTIVE | |
|
From: MEETING PL
To: MEETING PL
Scope: ASPHALT OVERLAY, FULL DEPTH RECLAMATION, AND VARIOUS METHODS OF ASPHALT SURFACE REFURBISHMENT THAT ARE APPLIED TO SEMINOLE COUNTY’S PAVED ROAD NETWORK. THIS INCLUDES LOCAL ROAD RESURFACING AND REHABILITATION THAT MAY INVOLVE RECONSTRUCTION ACTIVITY. THIS ALSO INCLUDES RESURFACING OF ARTERIAL/COLLECTOR ROADS NOT INVOLVING THE ROADWAY BASE. Phases:
Construction Start: 10/2009 End: 9/2010
|
||||
| OSCEOLA RD PAVEMENT MARKING PROJECT | STATE ROAD PROGRAM | Brett Blackadar
BBlackadar@seminolecountyfl.gov 407-665-5702 |
ACTIVE | |
|
From: SR 46
To: SEMINOLE CO LANDFILL
Scope: THIS PROJECT APPLY AUDIBLE PAVEMENT MARKINGS WHICH WILL BE ADDED TO THE CENTERLINE AND OUTSIDE EDGE LINES OF OSCEOLA RD. FLORIDA DEPARTMENT OF TRANSPORTATION AGREEMENT # APB 89 FLORIDA DEPARTMENT OF TRANSPORTATION ADDITIONAL ANTICIPATED AGREEMENT Phases:
Design Start: 1/2009 End: 8/2010
Construction Start: 7/2010 End: 8/2010 |
||||
| OSCEOLA RD. RESURFACING PROJECT | ARTERIAL/COLLECTOR PAVEMENT REHABILITATION - ROADS | Mike Van Der Heyden
mvanderheyden@seminolecountyfl.gov 407-665-5748 |
ACTIVE | |
|
From: KIMMIE KAY DR (WEST INTERSECTION)
To: LANDFILL ENTRANCE
Scope: ASPHALT OVERLAY, FULL DEPTH RECLAMATION, AND VARIOUS METHODS OF ASPHALT SURFACE REFURBISHMENT THAT ARE APPLIED TO SEMINOLE COUNTY`S PAVED ROAD NETWORK. THIS INCLUDES LOCAL ROAD RESURFACING AND REHABILITATION THAT MAY INVOLVE RECONSTRUCTION ACTIVITY. THIS ALSO INCLUDES RESURFACING OF ARTERIAL/COLLECTOR ROADS NOT INVOLVING THE ROADWAY BASE. Phases:
Road Construction Start: End:
|
||||
| OXFORD RD AT LAKE OF THE WOODS BLVD MAST ARMS | TRAFFIC SIGNALS | Charles Wetzel Iii | ACTIVE | |
|
From: N/A
To: N/A
Scope: CONVERSION OF AN EXISTING SPAN WIRE SIGNAL TO MAST ARMS. Phases:
Road Construction Start: 2/2009 End: 8/2009
|
||||
| PALM SPRINGS RD AT NORTH ST MAST ARMS | TRAFFIC SIGNALS | Charles Wetzel Iii | ACTIVE | |
|
From: N/A
To: N/A
Scope: CONVERSION OF AN EXISTING SPAN WIRE SIGNAL TO MAST ARMS. Phases:
Road Construction Start: 3/2009 End: 8/2009
|
||||
| PENFIELD CV AT MIDDLETON OAKS ASPHALT SURFACE AND PAVEMENT MANAGEMENT | RESURFACING | Harry Raysin
hraysin@seminolecountyfl.gov 407-665-2839 |
ACTIVE | |
|
From: MEETING PL
To: CUL DE SAC
Scope: ASPHALT OVERLAY, FULL DEPTH RECLAMATION, AND VARIOUS METHODS OF ASPHALT SURFACE REFURBISHMENT THAT ARE APPLIED TO SEMINOLE COUNTY’S PAVED ROAD NETWORK. THIS INCLUDES LOCAL ROAD RESURFACING AND REHABILITATION THAT MAY INVOLVE RECONSTRUCTION ACTIVITY. THIS ALSO INCLUDES RESURFACING OF ARTERIAL/COLLECTOR ROADS NOT INVOLVING THE ROADWAY BASE. Phases:
Construction Start: 10/2009 End: 9/2010
|
||||
| RED BUG LAKE RD AT ELEMENTARY SCHOOL PEDESTRIAN OVERPASS | PEDESTRIAN OVERPASSES / UNDERPASSES | Antoine Khoury
akhoury@seminolecountyfl.gov 407-665-5768 |
ACTIVE | |
|
From: N/A
To: N/A
Scope: DESIGN BUILD PEDESTRIAN OVERPASS Phases:
Land Start: 9/2005 End: 12/2006
Construction Start: 1/2010 End: 8/2011 |
||||
| RED BUG LAKE RD AT HOWELL CREEK EROSION CONTROL | SECONDARY SYSTEM STORMWATER PROJECT (SALES TAX) | Robert Walter
RWalter@seminolecountyfl.gov 407-665-5753 |
ACTIVE | |
|
From: TUSKAWILLA RD
To: RED BUG LAKE RD
Scope: EROSION CONTROL PROJECT UNDER RED BUG LAKE BRIDGE Phases:
Design Start: 12/2008 End: 8/2010
Land Start: 2/2010 End: 9/2010 Construction Start: 11/2010 End: 1/2012 |
||||
| RED BUG LAKE RD DETECTABLE WARNINGS | TRAFFIC SAFETY/RAILROAD CROSSING | Melonie Barrington
mbarrington@seminolecountyfl.gov 407-665-5676 |
ACTIVE | |
|
From: SR 436
To: SR 426
Scope: DETECTABLE WARNINGS. RECONSTRUCT 27 RAMPS AND INSTALL TRUNCATED DOMES ON A TOTAL OF 216 RAMPS FOR ADA COMPLIANCE. Phases:
Road Construction Start: 5/2009 End: 9/2009
|
||||
| RED BUG LAKE RD OUTFALL DRAINAGE IMPROVEMENTS | SECONDARY SYSTEM STORMWATER PROJECT (SALES TAX) | Robert Walter
RWalter@seminolecountyfl.gov 407-665-5753 |
ACTIVE | |
|
From: RED BUG LAKE RD
To: LAKE HOWELL
Scope: WATER QUALITY RETROFIT PROJECT ADDRESSING STORMWATER FROM RED BUG LAKE ROAD AND DEER RUN AREA. INCLUDES A WET RETENTION POND. Phases:
Design Start: 1/2007 End: 10/2009
Construction Start: 12/2009 End: 10/2010 |
||||
| RIDGEWOOD ST AND ALPINE ST SIDEWALK | SIDEWALK PROJECTS | Eric Erickson
eerickson@seminolecountyfl.gov 407-665-5666 |
ACTIVE | |
|
From: PALM SPRINGS DR
To: EVERGREEN AVE
Scope: THIS PROJECT WILL CONSTRUCT A NEW SIDEWALK ON RIDGEWOOD ST & ALPINE ST FROM PALM SPRINGS DR TO EVERGREEN AVE. THE TOTAL LENGTH OF THE NEW SIDEWALK IS APPROXIMATELY 4500 LINEAR FEET. 810 LF ON PALM SPRINGS DR HAS BEEN ADDED TO PROJECT. FLORIDA DEPARTMENT OF TRANSPORTATION ANTICIPATED AGREEMENT Phases:
Design Start: 2/2008 End: 1/2009
Construction Start: 4/2010 End: 7/2010 |
||||
| RISING SUN BLVD AT SUNRISE SUBDIVISION RETROFIT | SUBDIVISION REHABILITATION PROJECTS | Mark Flomerfelt
mflomerfelt@seminolecountyfl.gov 407-665-5709 |
ACTIVE | |
|
From: RED BUG LAKE RD
To: MAPIMI CT
Scope: DESIGN AND PIPELING FOR SUNRISE SUBDIVISION FROM RED BUG LAKE RD TO MAPIMI CT. Phases:
Design Start: End:
Construction Start: 10/2009 End: 2/2010 |
||||
| S SANFORD AVE AT LAKE MARY BLVD MAST ARM AND TURN LANES | TRAFFIC SIGNALS | Charles Wetzel Iii | ACTIVE | |
|
From: N/A
To: N/A
Scope: THIS PROJECT WILL DESIGN AND CONSTRUCT A NEW WARRANTED MAST ARM SIGNAL. THIS IS A HIGH PRIORITY PROJECT. Phases:
Design Start: 11/2007 End: 8/2008
Road Construction Start: 5/2009 End: 10/2009 |
||||
| S. CITRUS RD SIDEWALK | SIDEWALK PROJECTS | Brett Blackadar
BBlackadar@seminolecountyfl.gov 407-665-5702 |
ACTIVE | |
|
From: RED BUG LAKE ROAD
To: RAINBOW ELEMENTARY SCHOOL
Scope: RELOCATE UTILITIES AND REBUILD SIDEWALK TO PROVIDE SAFER PEDESTRIAN ROUTE FOR RAINBOW ELEMENTARY STUDENTS Phases:
Construction Start: 1/2010 End: 2/2010
|
||||
| SAND LAKE RD @ HUNT CLUB INTERSECTION IMPROVEMENTS | MINOR PROJECTS ROAD PROGRAM | Brett Blackadar
BBlackadar@seminolecountyfl.gov 407-665-5702 |
ACTIVE | |
|
From: SAND LAKE ROAD
To: HUNT CLUB INTERSECTION
Scope: THIS PROJECT CONSISTS OF EXTENDING THE LENGTH OF THE WESTBOUND RIGHT-TURN LANE AS WELL AS ADDING PEDESTIAN IMPROVMENTS TO THE INTERSECTION OF SAND LAKE RD AND HUNT CLUB BLVD. Phases:
Design Start: 12/2009 End: 9/2010
Road Construction Start: End: |
||||
| SEMINOLA BLVD AT WINTER PARK DR MAST ARMS | TRAFFIC SIGNALS | Charles Wetzel Iii | ACTIVE | |
|
From: N/A
To: N/A
Scope: CONVERSION OF AN EXISTING SPAN WIRE SIGNAL TO MAST ARMS. Phases:
Road Construction Start: 10/2008 End: 9/2009
|
||||
| SHADOW CREEK CIR AT CREEK WOOD SUBDIVISION RETROFIT | SUBDIVISION REHABILITATION PROJECTS | Mark Flomerfelt
mflomerfelt@seminolecountyfl.gov 407-665-5709 |
ACTIVE | |
|
From: MCCULLOCH RD
To: MCCULLOCH RD
Scope: CONSTRUCTION FOR CREEK WOOD SUBDIVISION FROM MCCULLOCH RD TO MCCULLOCH RD. Phases:
Construction Start: 12/2009 End: 2/2010
|
||||
| SNOWHILL RD OUTFALL JACOBS TRL ECONLOCKHATCHEE BASIN | PRIMARY SYSTEM STORMWATER PROJECT (SALES TAX) | Rolando Raymundo
RRaymundo@seminolecountyfl.gov 407-665-5715 |
ACTIVE | |
|
From: SNOWHILL RD
To: LAKE CRESENT DR
Scope: RECONSTRUCTION OF DITCHES AND OUTFALL FROM SNOWHILL RD TO LAKE CRESENT. DURING CONSTRUCTION OF JACOBS TRAIL AND THROUGH NATURAL OCCURRENCES THE DITCHES ALONG JACOBS TRAIL HAVE BEEN ALTERED AND DITCH BLOCKS WERE RENDERED INEFFECTIVE. THE PROJECT WILL RESTORE THESE DITCHES AND OUTFALL TO THEIR ORIGINAL CONDITIONS. Phases:
Design Start: 3/2008 End: 3/2010
Road Construction Start: 5/2010 End: 10/2010 |
||||
| SPRING VALLEY LOOP AT SPRING VALLEY FARMS SUBDIVISION RETROFIT | SUBDIVISION REHABILITATION PROJECTS | Mark Flomerfelt
mflomerfelt@seminolecountyfl.gov 407-665-5709 |
ACTIVE | |
|
From: SPRING VALLEY RD
To: SPRING VALLEY RD
Scope: DRAINAGE WORK FOR SPRING VALLEY FARMS SUBDIVISION FROM SPRING VALLEY RD TO SPRING VALLEY RD. Phases:
Construction Start: 12/2009 End: 2/2010
|
||||
| SR 426 AT ALOMA WOODS CONVEYANCE IMPROVEMENTS | SECONDARY SYSTEM STORMWATER PROJECT | Rolando Raymundo
RRaymundo@seminolecountyfl.gov 407-665-5715 |
ACTIVE | |
|
From: SR 426
To: BEAR GULLY CREEK
Scope: IMPROVEMENTS TO CONVEYANCE SYSTEM, INCLUDING UPSIZING PIPES AND POTENTIALLY CONSTRUCTING A POND FOR FLOOD ATTENUATION Phases:
Design Start: 7/2004 End: 9/2010
Construction Start: 10/2010 End: 9/2011 |
||||
| SR 426 CR 419 OVIEDO COST SHARED | UNIQUE MAJOR PROJECTS | Brett Blackadar
BBlackadar@seminolecountyfl.gov 407-665-5702 |
ACTIVE | |
|
From: PINE AVE
To: LOCKWOOD BLVD
Scope: THIS PROJECT WILL WIDEN SR 426 AND CR 419 FROM 2 TO 4 LANES AND WILL MAKE ADDITIONAL INTERSECTION IMPROVEMENTS. FLORIDA DEPARTMENT OF TRANSPORTATION AGREEMENT # 415030-1-38-01 BCC DATE 01/09/07, ACTION # 36, FUNDING AGREEMENT Phases:
Design Start: 10/2007 End: 3/2010
Land Start: 7/2013 End: 7/2013 Road Construction Start: 1/2016 End: 7/2017 |
||||
| SR 426 TURN LANES | MINOR PROJECTS ROAD PROGRAM | Ken Mickenberg
kmickenberg@seminolecountyfl.gov 407-665-5714 |
ACTIVE | |
|
From: TUSKAWILLA RD
To: SR 417
Scope: THIS PROJECT WILL CONVERT THE SOUTHBOUND THROUGH LANE ON TUSKAWILLA RD TO A LEFT THROUGH LANE AT THE SR 426 INTERSECTION. IN ADDITION, SR 426 WILL BE WIDENED FROM 4 LANE TO 6 LANES IN THIS SECTION. THE APPROXIMATE PROJECT LENGTH IS 0.4 MILES. THE SCOPE OF WORK ALSO INCLUDES SIGNAL RETIMING TO INTEGRATED ELECTRONIC CONTROLS OF THE REVAMPED INTERSECTION WITH OTHER INTERSECTIONS ALONG THE SR 426 CORRIDOR. Phases:
Design Start: 2/2006 End: 12/2009
Road Construction Start: 1/2010 End: 6/2010 |
||||
| SR 434 INTERSECTION IMPROVEMENTS | STATE ROAD PROGRAM | Shad Smith
ssmith@seminolecountyfl.gov 407-665-5707 |
ACTIVE | |
|
From: RANGELINE RD
To: CR 427
Scope: THIS PROJECT WILL PROVIDE INTERSECTION IMPROVEMENTS TO THIS URBAN SECTION OF ROADWAY AT CENTRAL FLA PKWY AND CR 427. PROJECT WILL INCLUDE RIGHT OF WAY ACQUISITION, WIDENING, RESURFACING, MAST ARM SIGNALS. THE APPROXIMATE LENGTH OF THE PROJECT IS 1.0 MILES. PRELIMINARY ENGINEERING STUDY UNDERWAY TO DETERMINE FINAL DESIGN ALTERNATIVE AS WELL AS ROW AND CONSTRUCTION COSTS. STUDY WILL BE SPLIT INTO TWO PARTS ONE FOR EACH INTERSECTION (CENTRAL FLA PARKWAY AND CR 426) FLORIDA DEPARTMENT OF TRANSPORTATION ANTICIPATED AGREEMENT Phases:
Design Start: 8/2008 End: 8/2010
Road Construction Start: 6/2013 End: 6/2015 |
||||
| SR 434 SEDIMENT BASIN LITTLE WEKIVA RIVER DRAINAGE | PRIMARY SYSTEM STORMWATER PROJECT (JPP) | Robert Walter
RWalter@seminolecountyfl.gov 407-665-5753 |
ACTIVE | |
|
From: SR 434
To: AT LITTLE WEKIVA RIVER
Scope: DESIGN OF A SEDIMENT COLLECTION BASIN ALONG THE LITTLE WEKIVA RIVER. PART OF A COMPREHENSIVE EROSION AND SEDIMENT CONTROL PLAN. ST JOHNS RIVER WATER MANAGEMENT DISTRICT AGREEMENT # SI440AA THIS PROJECT WAS PART OF AN ORIGINAL AGREEMENT WHICH INCLUDED FOUR OTHER PROJECTS (WEATHERSFIELD, SAN SEBASTIAN, NORTHWESTERN, AND HORSELOVERS LANE). UNDER THAT AGREEMENT THIS PROJECT INCURRED $71,948 IN EXPENDITURES THAT WERE REIMBURSED ACROSS FY 01 - 02 AND FY 02 - 03. ONLY PROJECT EXPENDITURES BEGINNING WITH FY 05 - 06 WILL BE ELIGIBLE FOR REIMBURSEMENT UNDER AGREEMENT SI440AA. Phases:
Design Start: 5/2007 End: 10/2009
Construction Start: 11/2009 End: 5/2010 |
||||
| SR 434 SIX LANING I-4 TO RANGELINE | STATE ROAD PROGRAM | Shad Smith
ssmith@seminolecountyfl.gov 407-665-5707 |
ACTIVE | |
|
From: I - 4
To: RANGELINE RD
Scope: THIS PROJECT WILL WIDEN URBAN ROADWAY SECTION FROM 4 TO 6 LANES. THE PROJECT LENGTH IS APPROXIMATELY 1.7 MILES. FLORIDA DEPARTMENT OF TRANSPORTATION ANTICIPATED AGREEMENT Phases:
Design Start: 2/2006 End: 9/2010
Land Start: 8/2008 End: 9/2010 Road Construction Start: 7/2013 End: 4/2015 |
||||
| SR 434 SIX LANING WIDEN FROM 4 TO 6 LANES | STATE ROAD PROGRAM | Brett Blackadar
BBlackadar@seminolecountyfl.gov 407-665-5702 |
ACTIVE | |
|
From: MONTGOMERY RD
To: I-4
Scope: WIDEN URBAN ROADWAY SECTION FROM 4 TO 6 LANES AND REPLACE BRIDGE OVER THE LITTLE WEKIVA RIVER. THE PROJECT LENGTH IS APPROXIMATELY 1.0 MILES FLORIDA DEPARTMENT OF TRANSPORTATION AGREEMENT # AP447 Phases:
Design Start: 6/2004 End: 8/2007
Land Start: 11/2006 End: 6/2008 Construction Start: 3/2009 End: 5/2010 Road Construction Start: 3/2009 End: 4/2010 |
||||
| SR 436 AT RED BUG LAKE RD INTERCHANGE | STATE ROAD PROGRAM | Shad Smith
ssmith@seminolecountyfl.gov 407-665-5707 |
ACTIVE | |
|
From: WILSHIRE BLVD
To: LAKE HOWELL RD.
Scope: THIS PROJECT WILL CREATE A PARTIAL INTERCHANGE AT SR 436 AND RED BUG LAKE RD THAT WILL INCLUDE A FLYOVER FOR SOUTHBOUND VEHICLES ON SR 436 TURNING ONTO EASTBOUND RED BUG LAKE RD. THE PROJECT WILL ALSO INCLUDE WIDENING PORTION OF RED BUG LAKE RD AND SR 436. MORE SPECIFIC PROJECT INFORMATION CAN BE FOUND AT THE FOLLOWING WEBSITE HTTP://65.202.76.58/ FLORIDA DEPARTMENT OF TRANSPORTATION AGREEMENT # 419369-1 FLORIDA DEPARTMENT OF TRANSPORTATION ADDITIONAL ANTICIPATED AGREEMENT ACCORDING TO AN EMAIL FROM BRETT BLACKADAR DATED 04/22/09 THERE WILL BE AN AGREEMENT WITH THE CITY OF CASSELBERRY TO MAINTAIN ALL OF THE PONDS AND THE LANDSCAPING IN THE MEDIANS ON ALL ROADS AFTER CONSTRUCTION IS COMPLETE. SR 436 AND THE ADJACENT PONDS WILL BE OWNED BY FDOT AND FOR RED BUG LAKE RD THE ADJACENT PONDS WILL BE OWNED BY SEMINOLE COUNTY. Phases:
Design Start: 9/2003 End: 8/2008
Land Start: 3/2008 End: 2/2010 Road Construction Start: 1/2011 End: 7/2013 |
||||
| SR 46 AND SR 415 E LAKE MARY BLVD INTERSECTION IMPROVEMENTS | MINOR PROJECTS ROAD PROGRAM | Shad Smith
ssmith@seminolecountyfl.gov 407-665-5707 |
ACTIVE | |
|
From: 250` SOUTH ON E. LAKE MARY BLVD.
To: 700` NORTH OF KLONDIKE WAY
Scope: THIS PROJECT WILL ADD ADDITIONAL NB AND SB THROUGH LANES AT THE INTERSECTION. THE INTERSECTION IS EXPERIENCING OPERATIONAL DELAYS DUE TO THE ADDITION OF THE EAST LAKE MARY BLVD EXTENSION TO THE SOUTH AND DUE TO NEW DEVELOPMENTS IN THE AREA. Phases:
Design Start: 4/2009 End: 12/2009
|
||||
| SR 46 GATEWAY SIDEWALK LOCAL AGENCY PROGRAM | SIDEWALK PROJECTS | David Martin
dmartin02@seminolecountyfl.gov 407-665-5610 |
ACTIVE | |
|
From: RINEHART RD
To: AIRPORT BLVD
Scope: DESIGN AND CONSTRUCT SIDEWALKS ALONG 2.0 MILES OF SR 46 IN SANFORD. INCLUDES 10 FOOT SIDEWALK ALONG NORTH SIDE OF SR 46 AND 5 FOOT SIDEWALK ALONG SOUTH SIDE. ADDITIONAL RIGHT OF WAY OR EASEMENTS WILL NEED TO BE ACQUIRED THROUGH DONATION TO AND MAINTAINED BY THE CITY OF SANFORD. THIS WILL BE APPROXIMATELY 10,316 LINEAR FEET OF SIDEWALKS. THIS IS A FLORIDA DEPARTMENT OF TRANSPORTATION LOCAL AGENCY PROGRAM PROJECT WITH REIMBURSEMENT FOR DESIGN AND CONSTRUCTION. FLORIDA DEPARTMENT OF TRANSPORTATION AGREEMENT # AO857 FLORIDA DEPARTMENT OF TRANSPORTATION ADDITIONAL ANTICIPATED AGREEMENT Phases:
Design Start: 2/2008 End: 12/2009
Road Construction Start: 11/2009 End: 6/2010 |
||||
| SR 46 NEW FIBER OPTIC CONSTRUCTION | TRAFFIC FIBER OPTIC AND ATMS NETWORK | Charles Wetzel Iii | ACTIVE | |
|
From: US 17-92
To: MELLONVILLE
Scope: INSTALLATION OF NEW FIBER FOR INCREASED CAPACITY AND REDUNDANCY. Phases:
Road Construction Start: 2/2009 End: 9/2009
|
||||
| ST JOHNS RIVER BASIN - MULLET LAKE PARK ROAD RSF PROJECT | PRIMARY SYSTEM STORMWATER PROJECT | Mark Flomerfelt
mflomerfelt@seminolecountyfl.gov 407-665-5709 |
ACTIVE | |
|
Scope: PROJECT IS A REGIONAL STORMWATER FACILITY (RSF) TO REMOVE PHOSPHORUS AND NITROGEN FROM THE ST JOHNS RIVER BASIN.
Phases:
Design Start: 10/2012 End: 9/2013
Land Start: 10/2013 End: 9/2014 Construction Start: 10/2014 End: 9/2015 |
||||
| STILLWATER DR AT STILLWATER SUBDIVISION RETROFIT | SUBDIVISION REHABILITATION PROJECTS | Mark Flomerfelt
mflomerfelt@seminolecountyfl.gov 407-665-5709 |
ACTIVE | |
|
From: SR 434
To: BROWARD CT
Scope: ENGINEERING DESIGN AND CAMERA INSPECTION FOR STILLWATER SUBDIVISION FROM SR 434 TO BROWARD CT. Phases:
Design Start: 3/2009 End: 9/2010
|
||||
| SWEETWATER COVE TRIBUTARY DREDGING AND DRAINAGE IMPROVEMENTS | PRIMARY SYSTEM STORMWATER PROJECT (JPP) | Robert Walter
RWalter@seminolecountyfl.gov 407-665-5753 |
ACTIVE | |
|
From: WEKIVA SPRINGS RD
To: WEKIVA RIVER
Scope: SEDIMENT DREDGING OF SWEETWATER COVE ALONG WITH STRUCTURE MODIFICATIONS AND LITTORAL PLANTING. (WETLAND PLANTS AROUND THE EDGE OF A LAKE) ST JOHNS RIVER WATER MANAGEMENT DISTRICT AGREEMENT # SE621AA Phases:
Design Start: 3/2006 End: 3/2008
Construction Start: 3/2009 End: 12/2009 |
||||
| SYLVAN LAKE OUTFALL LAKE LEVEL CONTROL | SECONDARY SYSTEM STORMWATER PROJECT (SALES TAX) | Robert Walter
RWalter@seminolecountyfl.gov 407-665-5753 |
ACTIVE | |
|
From: LAKE SYLVAN
To: WEKIVA RIVER
Scope: LAKE LEVEL CONTROL CONSISTING OF SURFACE WATER MODIFICATIONS AND IRRIGATION FROM THE LAKE Phases:
Construction Start: 10/2007 End: 5/2011
|
||||
| US 17-92 AT BUTTON RD MAST ARMS | TRAFFIC SIGNALS | Charles Wetzel Iii | ACTIVE | |
|
From: N/A
To: N/A
Scope: CONVERSION OF AN EXISTING SPAN WIRE SIGNAL TO MAST ARMS. Phases:
Road Construction Start: 2/2008 End: 9/2009
|
||||
| US 17-92 AT SEMINOLA BLVD AND DOG TRACK MAST ARMS | TRAFFIC SIGNALS | Charles Wetzel Iii | ACTIVE | |
|
From: N/A
To: N/A
Scope: CONVERSION OF AN EXISTING SPAN WIRE SIGNAL TO MAST ARMS. Phases:
Road Construction Start: 2/2008 End: 9/2009
|
||||
| US 17-92 LAKEFRONT RIVERWALK CITY OF SANFORD LEAD | UNIQUE MAJOR PROJECTS | David Martin
dmartin02@seminolecountyfl.gov 407-665-5610 |
ACTIVE | |
|
From: FULTON RD
To: I-4
Scope: CITY OF SANFORD PROJECT Phases:
Road Construction Start: End:
|
||||
| W 27TH ST SIDEWALK | SIDEWALK PROJECTS | David Andrews, Jr.
dandrews@seminolecountyfl.gov 407-665-5716 |
ACTIVE | |
|
From: US 17-92
To: SANFORD AVE
Scope: CONSTRUCT 3,000 LINEAR FEET OF SIDEWALK ON NORTH SIDE OF W 27TH ST FROM US 17-92 TO SANFORD AVE Phases:
Design Start: 4/2008 End: 5/2009
Land Start: 10/2008 End: 9/2009 Construction Start: 10/2009 End: 12/2009 |
||||
| W CRYSTAL DR DRAINAGE IMPROVEMENTS | SECONDARY SYSTEM STORMWATER PROJECT (SALES TAX) | Mark Flomerfelt
mflomerfelt@seminolecountyfl.gov 407-665-5709 |
ACTIVE | |
|
From: COUNTRY CLUB RD
To: LAKE BLVD
Scope: MISCELLANEOUS ROADWAY DRAINAGE IMPROVEMENTS ALONG WITH WATER QUALITY RETROFIT FOR THE AREA. Phases:
Design Start: 1/2009 End: 12/2009
Construction Start: End: |
||||
| W LAKE MARY BLVD AND LAKE EMMA RD INTERSECTION IMPROVEMENTS | MINOR PROJECTS ROAD PROGRAM | ACTIVE | ||
|
From: INTERSECTION
To: INTERSECTION
Scope: ADDITION OF A 2ND EASTBOUND RIGHT TURN LANE. Phases:
Construction Start: 10/2009 End: 9/2010
|
||||
| WEKIVA PARK DR OUTFALL IMPROVEMENTS | SECONDARY SYSTEM STORMWATER PROJECT (SALES TAX) | Rolando Raymundo
RRaymundo@seminolecountyfl.gov 407-665-5715 |
ACTIVE | |
|
From: SR 46
To: END OF ROAD
Scope: REPLACEMENT AND UPSIZING OF SEVERAL CROSSDRAINS INTO THE WEKIVA RIVER Phases:
Design Start: 9/2005 End: 10/2008
Land Start: 6/2005 End: 11/2009 Construction Start: 12/2008 End: 8/2009 |
||||
| WEKIVA TRL AT WEKIVA CLUB SUBDIVISION RETROFIT | SUBDIVISION REHABILITATION PROJECTS | Mark Flomerfelt
mflomerfelt@seminolecountyfl.gov 407-665-5709 |
ACTIVE | |
|
From: HUNT CLUB BLVD
To: HUNT CLUB BLVD
Scope: PIPELINING FOR WEKIVA CLUB SUBDIVISION FROM HUNT CLUB BLVD TO HUNT CLUB BLVD. Phases:
Construction Start: 12/2007 End: 9/2009
|
||||
| WHISPERING WINDS POND RETROFITS | ROADS/STORMWATER WATER QUALITY/TMDL | Kimberly Ornberg
kornberg@seminolecountyfl.gov 407-665-5738 |
MONITORING | |
|
From: NA
To: NA
Scope: THE PURPOSE OF THIS PROJECT IS TO REPAIR/RECONSTRUCT TO 3 PONDS LOCATED WITHIN THE WHISPERING WINDS SUBDIVISION, WHICH DRAIN TO THE LITTLE WEKIVA RIVER (AN DEPARTMENT OF ENVIRONMENTAL PROTECTION TOTAL MAXIMUM DAILY LOAD IMPAIRED WATERBODY). THE PROPOSED RETROFITS WILL BRING THE PONDS INTO PERMIT COMPLIANCE WITH ST JOHNS RIVER WATER MANAGMENT DISTRICT. , AS WELL AS INCREASE THE WATER QUALITY TREATMENT CURRENTLY PROVIDED BY THE PONDS (THUS PROVIDING TOTAL MAXIMUM DAILY LOAD WATER QUALITY CREDITS FOR THE LITTLE WEKIVA BASIN). Phases:
Construction Start: End:
|
||||
| WIRZ PARK TRL CITY OF CASSELBERRY LEAD | TRAILS | David Martin
dmartin02@seminolecountyfl.gov 407-665-5610 |
ACTIVE | |
|
From: KEWANNEE PARK
To: WIRZ PARK
Scope: REIMBURSEMENT/FRONTING OF FUNDS FOR DESIGN AND CONSTRUCTION OF A 1.6 MILE SECTION OF 10-FOOT WIDE TRAIL. Phases:
Construction Start: 10/2007 End: 9/2010
|
||||
| WYMORE RD ADD CENTER LANE | MAJOR ROAD PROGRAM | Shad Smith
ssmith@seminolecountyfl.gov 407-665-5707 |
ACTIVE | |
|
From: ORANGE COUNTY LINE
To: SR 436
Scope: THIS PROJECT CONSISTS OF RECONSTRUCTING THE EXISTING TWO LANE ROAD. THE RECONSTRUCTION WILL WIDEN THE ROADWAY FROM ITS CURRENT TWO LANES BY ADDING A CENTER MEDIAN WITH TURN LANES AND OTHER SAFETY AND DRAINAGE IMPROVEMENTS. THE PROJECT LENGTH IS 1.3 MILES Phases:
Design Start: 7/2004 End: 11/2008
Land Start: 10/2004 End: 9/2013 Road Construction Start: 11/2013 End: 8/2015 |
||||
| WYMORE RD AND ORANOLE INTERSECTION IMPROVEMENTS | MINOR PROJECTS ROAD PROGRAM | ACTIVE | ||
|
From: INTERSECTION
To: INTERSECTION
Scope: ADD EAST BOUND AND NORTH BOUND RIGHT TURN LANES TO THE INTERSECTION. Phases:
Design Start: 10/2009 End: 9/2010
Road Construction Start: 10/2010 End: 9/2011 |
||||
| WYMORE RD SIDEWALK | SIDEWALK PROJECTS | Ken Mickenberg
kmickenberg@seminolecountyfl.gov 407-665-5714 |
ACTIVE | |
|
From: SR 436
To: LAKE DESTINY RD
Scope: THE PROJECT WILL ADD APPROXIMATELY 1.3 MILES OF SIDEWALK THAT WILL NEED TO BE MAINTAINED BY THE PUBLIC WORKS/ROADS DIVISION. Phases:
Design Start: 4/2009 End: 12/2009
Construction Start: 2/2010 End: 5/2010 |
||||
Total Number of projects: 120