PROJECT ID |
|
|
LAKE HOWELL HIGH SCHOOL TRAFFIC CIRCULATION FEASIBILITY STUDY
Project Type: Traffic Safety
Project Manager:
Melonie Barrington - 407-665-5676
Status: Active
Scope: THIS INTIAL PHASE OF THE PROJECT IS A FEASIBILITY STUDY DETERMINING WHICH OF THE FOLLOWING OPTIONS WOULD BEST IMPROVE TRAFFIC CIRCULATION AT THE SCHOOL;
-ADDITIONAL DRIVEWAY CONNECTION TO DIKE RD.(INCLUDING PROVISION FOR RIGHT TURN LANE).
-RECONFIGURATION OF PARKING AT THE DRIVER EDUCATION AREA
-STUDY OF EXISTION MAIN CAMPUS DRIVEWAY CONNECTION TO DIKE RD.
-RECONFIGURATION OF ON SITE DRIVEWAYS AND PARKING AREAS
THE REMAINING FUNDS WOULD PARTIALLY FUND WHICHEVER ALTERNATIVE IS SELECTED.
Phases:
Design Start: - End: - Road Construction Start: - End: -
|
|
LAKE HOWELL RD PH 2 PAVEMENT REHABILITATION
Project Type: Paving
Project Manager:
Harry Raysin - 407-665-2839
Status: Active
From: ORANGE COUNTY LINE
To: HOWELL BRANCH RD
Scope: ASPHALT OVERLAY, FULL DEPTH RECLAMATION, AND/OR VARIOUS REHABILITATION METHODS. (I.E. PIPE LINING OR REPLACEMENT, MILL AND RESURFACE). (COLLECTOR)
Phases:
Construction Start: 6/2009 End: 9/2009
|
|
LAKE JESUP BASIN RSF (NAVY CANAL/SJRWMD MITIGATION)
Project Type: Stormwater
Project Manager:
Robert Walter - 407-665-5753
Status: Monitoring
From: E LAKE MARY BLVD
To: SOUTH OF SAND DOLLAR PT
Scope: THIS PROJECT WILL MITIGATE THE CONSTRUCTION OF REGIONAL STORMWATER FACILITY FOR FLOOD ATTENUATION AND WATER QUALITY TREATMENT.
FLORIDA DEPARTMENT OF ENVIORNMENTAL PROTECTION AGREEMENT # S0341
BCC DATE 08/28/07, ACTION # 38, FUNDING AGREEMENT
Phases:
Design Start: 3/2003 End: 11/2006 Land Start: 10/2003 End: 9/2004 Construction Start: 4/2006 End: 11/2007
|
|
LAKE JESUP TMDL PROJECT - HOWELL CREEK ALUM PROJECT
Project Type: Stormwater
Project Manager:
Kimberly Ornberg - 407-665-5738
Status: Active
Scope: PROJECT IS A REGIONAL STORMWATER FACILITY (RSF) TO REMOVE PHOSPHORUS FROM HOWELL CREEK, ULTIMATELY LAKE HOWELL AND LAKE JESUP.
Phases:
Design Start: 10/2011 End: 9/2012 Land Start: 10/2010 End: 9/2011 Construction Start: 10/2012 End: 9/2013
|
|
LAKE JESUP TMDL PROJECT - SOLDIERS CREEK AT CR 427 RSF
Project Type: Stormwater
Project Manager:
Mark Flomerfelt - 407-665-5709
Status: Active
Scope: PROJECT IS A REGIONAL STORMWATER FACILITY (RSF) TO REMOVE PHOSPHORUS FROM SOLDIERS CREEK, ULTIMATELY LAKE JESUP.
Phases:
Design Start: 11/2009 End: 9/2010 Construction Start: 1/2011 End: 9/2011
|
|
LAKE MARY BLVD AT INTERNATIONAL PKWY PEDESTRIAN OVERPASS
Project Type: Overpasses
Project Manager:
David Martin - 407-665-5610
Status: Active
From: N/A
To: N/A
Scope: CONSTRUCT A PEDESTRIAN UNDERPASS TO CROSS PEDESTRIANS SAFELY PAST THE INTERSECTION OF LAKE MARY BLVD AT INTERNATIONAL PKWY. DESIGN IS UNDERWAY.
Phases:
Design Start: 2/2006 End: 12/2009 Construction Start: 1/2010 End: 6/2011
|
|
LAKE MARY BLVD AT SUN DR SECONDARY DRAINAGE
Project Type: Stormwater
Project Manager:
Rolando Raymundo - 407-665-5715
Status: Active
From: RINEHART RD
To: LAKE EMMA RD
Scope: PRELIMINARY ENGINEERING DESIGN FOR SECONDARY DRAINAGE ON LAKE MARY BLVD AND OUTFALL ALONG SUN DR.
Phases:
Design Start: 12/2008 End: 10/2010 Construction Start: 11/2010 End: 10/2011
|
|
LAKE MARY BLVD AT US 17-92 INTERSECTION IMPROVEMENTS
Project Type: Roadway Projects
Project Manager:
Ken Mickenberg - 407-665-5714
Status: Closeout Transition
From: INTERSECTION
To: INTERSECTION
Scope: THIS PROJECT WILL ADD A RIGHT TURN LANE TO THE INTERSECTION ON LAKE MARY BLVD ONTO NORTHBOUND US 17-92.
Phases:
Design Start: 11/2007 End: 1/2009 Road Construction Start: 5/2009 End: 8/2009
|
|
LINCOLN HEIGHTS DRAINAGE IMPROVEMENTS
Project Type: Stormwater
Project Manager:
Robert Walter - 407-665-5753
Status: Active
From: AIRPORT BLVD
To: LINCOLN AVE
Scope: MAJOR FLOOD ATTENUATION PROJECT ADDRESSING THE CHRONIC FLOODING OF THE LINCOLN HEIGHTS SUBDIVISION.
Phases:
Design Start: 9/2007 End: 12/2009 Land Start: 1/2007 End: 11/2009 Construction Start: 1/2010 End: 12/2010
|
|
LOCKHART SMITH REGIONAL FACILITY
Project Type: Stormwater
Project Manager:
Rolando Raymundo - 407-665-5715
Status: Active
From: 500` W OF INTERSTATE 4
To: 1/2 MILE NORTH OF SR 46
Scope: CONSTRUCTION OF REGIONAL STORMWATER POND AT SITE FORMALLY KNOWN AS I-4 BORROW PIT.
FLORIDA DEPARTMENT OF TRANSPORTATION AGREEMENT # S0261
Phases:
Construction Start: 1/2007 End: 9/2007
|
|
LOCKWOOD BLVD DETECTABLE WARNINGS
Project Type: Traffic Safety
Project Manager:
Melonie Barrington - 407-665-5676
Status: Active
From: MCCULLOCH RD
To: SOUTH TO END OF COUNTY MAINTAINED ROADWAY
Scope: DETECTABLE WARNINGS. RECONSTRUCT 14 RAMPS AND INSTALL 50 TRUNCATED DOMES FOR ADA COMPLIANCE.
Phases:
Road Construction Start: 6/2009 End: 9/2009
|
|
LONGWOOD LAKE MARY RD CENTER TURN LANE
Project Type: Roadway Projects
Project Manager:
Harry Raysin - 407-665-2839
Status: Active
From: LAKE PARK RD
To: GREENWAY BLVD
Scope: THIS PROJECT WILL RECONSTRUCT THE ROADWAY TO IMPROVE THE PAVEMENT CONDITION. A PORTION OF THE ROADWAY BETWEEN LAKE PARK DR AND LAKE MARY HIGH SCHOOL WAS COMPLETED IN DECEMBER 2008.
Phases:
Design Start: 2/2008 End: 9/2008 Land Start: 6/2009 End: 7/2010 Road Construction Start: 12/2009 End: 11/2010
|
|
LONGWOOD-MARKHAM RD/ MARKHAM RD SIDEWALK
Project Type: Sidewalk Projects
Project Manager:
Ken Mickenberg - 407-665-5714
Status: Active
From: RAMBLING RIVER DR
To: MARKHAM RD TRAILHEAD
Scope: THIS PROJECT WILL CONSTRUCT 760 LINEAR FEET OF SIDEWALK ON WEST SIDE OF LONGWOOD MARKHAM RD, SOUTH FROM RAMBLING RIVER DR AND 2,670` LINEAR FEET OF SIDEWALK ON THE EAST SIDE OF LONGWOOD MARKHAM RD EAST TO THE MARKHAM ROAD TRAILHEAD WITHIN THE RAILROAD RIGHT OF WAY ON THE NORTH SIDE OF MARKHAM RD.
Phases:
Design Start: 4/2008 End: 1/2010 Construction Start: 3/2010 End: 7/2010
|
|
MAGNOLIA AVE UNPAVED ROADS
Project Type: Roadway Projects
Project Manager:
Jimmie Beach, Jr. - 407-665-5606
Status: Active
From: 27TH ST
To: SOUTH TO PAVEMENT
Scope: PROJECT LENGTH IS 0.26 MILES. WORK ASSOCIATED WITH THE APPLICATION OF AN ALTERNATIVE SURFACE TREATMENT (DRAINAGE IMPROVEMENTS, BASE RECONSTRUCTION, AND ASPHALT PAVING)
Phases:
Land Start: 7/2006 End: 4/2008 Road Construction Start: 7/2008 End: 9/2009
|
|
MAITLAND AVE DETECTABLE WARNINGS
Project Type: Traffic Safety
Project Manager:
Melonie Barrington - 407-665-5676
Status: Active
From: SR 436
To: SOUTH TO COUNTY LINE
Scope: DETECTABLE WARNINGS. RECONSTRUCT 7 RAMPS AND INSTALL TRUNCATED DOMES FOR ADA COMPLIANCE.
Phases:
Road Construction Start: 6/2009 End: 9/2009
|
|
MARKHAM WOOD GRAVITY WALL
Project Type: Roadway Projects
Project Manager:
Mike Van Der Heyden - 407-665-5748
Status: Active
From: NA
To: NA
Scope: THIS PROJECT WILL REPAIR GRAVITY WALL ON MARKHAM WOODS RD.
Phases:
Construction Start: 6/2009 End: 7/2009
|
|
MARKHAM WOODS RD ADD CENTER LANE PH 1
Project Type: Roadway Projects
Project Manager:
Brett Blackadar - 407-665-5702
Status: Active
From: EE WILLIAMSON RD
To: MARKHAM RD
Scope: THIS PROJECT WILL ADD LEFT TURN LANES AT 7 LOCATIONS AND WILL EXTEND THE EXISTING LEFT TURN LANE AT EE WILLIAMSON RD. THIS PROJECT WILL ALSO IMPROVE THE EXISTING PAVEMENT FOR THE SECTION NORTH OF LAKE MARY BLVD. THE PROJECT LENGTH IS APPROXIMATELY 5.0 MILES.
Phases:
Design Start: 2/2007 End: 1/2009 Land Start: 10/2007 End: 9/2008 Road Construction Start: 5/2009 End: 10/2009
|
|
MCCULLOCH RD DETECTABLE WARNINGS
Project Type: Traffic Safety
Project Manager:
Melonie Barrington - 407-665-5676
Status: Active
From: SR 434
To: LOCKWOOD BLVD
Scope: DETECTABLE WARNINGS. RECONSTRUCT 1 RAMP AND INSTALL 30 TRUNCATED DOMES FOR ADA COMPLIANCE.
Phases:
Road Construction Start: 6/2009 End: 9/2009
|
|
MIDWAY ELEMENTARY SCHOOL SIDEWALK
Project Type: Sidewalk Projects
Project Manager:
Ken Mickenberg - 407-665-5714
Status: Active
From: MIDWAY ELEMENTARY SCHOOL
To: SURROUNDING AREAS
Scope: CONSTRUCT 11,850 LINEAR FEET OF SIDEWALKS TO CONNECT TO NEW MIDWAY ELEMENTARY SCHOOL. INCLUDES 4000 LF ON BRISSON AVE. 1650 LF ON KINGS RD. 1300 LF ON CRAWFORD DR. 1300 LF ON BYRD AVE. 1100 LF ON GRANBY ST. 1000 LF ON E. 20TH STREET. 650 LF ON RUFF RD. 500 LF ON JITWAY AVE. 350 LF ON LINGARD AVE.
Phases:
Design Start: 4/2009 End: 1/2010 Construction Start: 3/2010 End: 6/2010
|
|
MIDWAY REGIONAL STORMWATER FACILITY DEMOLITION
Project Type: Stormwater
Project Manager:
Robert Walter - 407-665-5753
Status: Active
From: CELERY AVE
To: SIPES AVE
Scope: DEMOLITION IN PREPARATION OF DESIGN OF A REGIONAL STORMWATER FACILITY PROVIDING FLOOD ATTENUATION AND WATER QUALITY TREATMENT FOR THE MIDWAY AREA.
SAINT JOHNS RIVER WATER MANAGEMENT AGREEMENT # SJ456AA
BCC DATE 06/27/06, ACTION # 34, FUNDING AGREEMENT
Phases:
Land Start: 3/2007 End: 5/2010 Construction Start: 2/2007 End: 5/2010
|
|
MIKLER RD SIDEWALK
Project Type: Sidewalk Projects
Project Manager:
Ken Mickenberg - 407-665-5714
Status: Active
From: RED BUG LAKE RD
To: MORNING STAR PL
Scope: THIS PROJECT WILL CONSTRUCT MISSING GAPS ON APPROXIMATELY 2,700 LINEAR FEET ON MIKLER RD BETWEEN RED BUG LAKE RD AND MORNING STAR PL.
Phases:
Design Start: 3/2009 End: 10/2009 Construction Start: 1/2010 End: 3/2010
|
|
NORTH ST PAVEMENT REHABILITATION
Project Type: Paving
Project Manager:
Status: Active
From: COUNTRY CLUB RD
To: SEMINOLE AVE
Scope: ASPHALT OVERLAY, FULL DEPTH RECLAMATION, AND/OR VARIOUS REHABILITATION METHODS. (I.E. PIPE LINING OR REPLACEMENT, MILL AND RESURFACE). (COLLECTOR).
Phases:
Construction Start: 3/2009 End: 6/2009
|
|
OLD LAKE MARY RD PAVEMENT REHABILITATION PH 1
Project Type: Paving
Project Manager:
Harry Raysin - 407-665-2839
Status: Active
From: N PALMETTO ST
To: AIRPORT BLVD
Scope: ASPHALT OVERLAY, FULL DEPTH RECLAMATION, AND/OR VARIOUS REHABILITATION METHODS. (I.E. PIPE LINING OR REPLACEMENT, MILL AND RESURFACE). (COLLECTOR)
Phases:
Construction Start: 4/2009 End: 6/2009
|
|
OLD MAIL LN AT MIDDLETON OAKS ASPHALT SURFACE AND PAVEMENT MANAGEMENT
Project Type: Paving
Project Manager:
Harry Raysin - 407-665-2839
Status: Active
From: MEETING PL
To: MEETING PL
Scope: ASPHALT OVERLAY, FULL DEPTH RECLAMATION, AND VARIOUS METHODS OF ASPHALT SURFACE REFURBISHMENT THAT ARE APPLIED TO SEMINOLE COUNTY’S PAVED ROAD NETWORK. THIS INCLUDES LOCAL ROAD RESURFACING AND REHABILITATION THAT MAY INVOLVE RECONSTRUCTION ACTIVITY. THIS ALSO INCLUDES RESURFACING OF ARTERIAL/COLLECTOR ROADS NOT INVOLVING THE ROADWAY BASE.
Phases:
Construction Start: 10/2009 End: 9/2010
|
|
OSCEOLA RD PAVEMENT MARKING PROJECT
Project Type: Roadway Projects
Project Manager:
Brett Blackadar - 407-665-5702
Status: Active
From: SR 46
To: SEMINOLE CO LANDFILL
Scope: THIS PROJECT APPLY AUDIBLE PAVEMENT MARKINGS WHICH WILL BE ADDED TO THE CENTERLINE AND OUTSIDE EDGE LINES OF OSCEOLA RD.
FLORIDA DEPARTMENT OF TRANSPORTATION
AGREEMENT # APB 89
FLORIDA DEPARTMENT OF TRANSPORTATION
ADDITIONAL ANTICIPATED AGREEMENT
Phases:
Design Start: 1/2009 End: 8/2010 Construction Start: 7/2010 End: 8/2010
|