PROJECT ID |
|
|
CR 427 AND NORTH ST INTERSECTION IMPROVEMENTS
Project Type: Roadway Projects
Project Manager:
Status: Active
From: INTERSECTION
To: INTERSECTION
Scope: ADDITION OF A SOUTHBOUND RIGHT TURN LANE.
Phases:
Design Start: 10/2009 End: 9/2010 Land Start: 10/2009 End: 9/2010
|
|
CR 427 FIBER OPTIC UPGRADE
Project Type: Traffic
Project Manager:
Charles Wetzel III - 407-665-5686
Status: Active
From: US 17-92
To: LAKE MARY BLVD
Scope: UPGRADE OF EXISTING FIBER FOR INCREASED CAPACITY.
Phases:
Road Construction Start: 2/2009 End: 9/2009
|
|
CR 431 AT ORANGE BLVD DRAINAGE IMPROVEMENTS
Project Type: Roadway Projects
Project Manager:
Eric Erickson - 407-665-5666
Status: Active
From: CR 46A
To: SR 46
Scope: CREATE A THREE LANE SECTION WITH A BI-DIRECTIONAL TURN LANE AND IMPROVE DRAINAGE. THE PROJECT LENGTH IS 1.7 MILES
Phases:
Design Start: 3/2004 End: 10/2010 Road Construction Start: 5/2008 End: 10/2009
|
|
CR 46A AT COLONIAL PKWY INTERSECTION IMPROVEMENTS
Project Type: Roadway Projects
Project Manager:
Brett Blackadar - 407-665-5702
Status: Active
From: INTERSECTION
To: INTERSECTION
Scope: THIS PROJECT WILL ADD A WESTBOUND RIGHT TURN LANE TO THE INTERSECTION.
Phases:
Design Start: 1/2008 End: 12/2008 Road Construction Start: 1/2009 End: 3/2009
|
|
CR 46A WALLS & LANDSCAPING
Project Type: Roadway Projects
Project Manager:
David Andrews, Jr. - 407-665-5716
Status: Active
From: CR 15
To: OLD LAKE MARY RD
Scope: THIS PROJECT WILL BUILD A SIX FOOT HIGH WALL FOR LOCH ARBOR SUBDIVISION AND TWO PRIVACY WALLS LOCATED ON CR 46A. THE PROJECT WILL ALSO INCLUDE TREE REMOVAL FOR LOCH ARBOR SUBDIVISION WALL, LANDSCAPING OF POND, AND LANDSCAPING ALONG THE CR 46A ROADWAY.
Phases:
Road Construction Start: 7/2009 End: 12/2009
|
|
CROSS SEMINOLE TRL PH III
Project Type: Trail Projects
Project Manager:
David Martin - 407-665-5610
Status: Closeout Transition
From: SR 426
To: SR 434
Scope: CONSTRUCTION OF APPROXIMATELY 1.0 MILES OF TRAIL, 6 TO 8 FOOT WIDE UNPAVED PATH AND .75 MILES OF WETLAND RESTORATION FROM SR 426 TO SR 434.
FLORIDA DEPARTMENT OF TRANSPORTAION
AGREEMENT # 413747-1-58-01
Phases:
Construction Start: 6/2008 End: 5/2009 Road Construction Start: 6/2008 End: 5/2009
|
|
CROSS SEMINOLE TRL SOUTH II
Project Type: Trail Projects
Project Manager:
David Martin - 407-665-5610
Status: Closeout Transition
From: MIKLER ROAD
To: RED BUG LAKE RD
Scope: CONSTRUCTION OF APPROXIMATELY 1.8 MILES OF 14 FOOT WIDE TRAIL WITHIN FLORIDA DEPARTMENT OF TRANSPORTATION`S SR 426 RIGHT OF WAY.
FLORIDA DEPARTMENT OF TRANSPORTATION AGREEMENT # AP360
Phases:
Construction Start: 8/2008 End: 5/2009
|
|
DEAN RD WIDEN FROM 2 TO 4 LANES
Project Type: Roadway Projects
Project Manager:
Brett Blackadar - 407-665-5702
Status: Active
From: SR 426
To: ORANGE COUNTY LINE
Scope: THIS PROJECT WILL WIDEN THE ROADWAY FROM 2 TO 4 LANES. THE APPROXIMATE LENGTH IS 0.6 MILES
Phases:
Design Start: 11/2009 End: 12/2011 Land Start: 10/2010 End: 9/2011 Road Construction Start: 10/2012 End: 9/2013
|
|
DODD RD DETECTABLE WARNINGS
Project Type: Traffic Safety
Project Manager:
Melonie Barrington - 407-665-5676
Status: Active
From: EAGLE BLVD
To: HOWELL BRANCH RD
Scope: INSTALL DETECTABLE WARNINGS. RECONSTRUCT 2 RAMPS AND INSTALL 31 TRUNCATED DOMES FOR ADA COMPLIANCE.
Phases:
Road Construction Start: 6/2009 End: 9/2009
|
|
DYSON DR SIDEWALK PH 1
Project Type: Sidewalk Projects
Project Manager:
David Andrews, Jr. - 407-665-5716
Status: Active
From: TUSKAWILLA RD
To: SHETLAND RD
Scope: THIS PROJECT WILL CONSTRUCT APPROXIMATELY 3,100 LINEAR FEET OF SIDEWALK ON BOTH SIDES OF DYSON DRIVE FROM TUSKAWILLA ROAD TO HOWELL CREEK. THE PROJECT INCLUDES DRAINAGE IMPROVEMENTS AND A NEW PEDESTRIAN BRIDGE OVER HOWELL CREEK.
Phases:
Design Start: 6/2004 End: 3/2009 Construction Start: 6/2009 End: 10/2009
|
|
DYSON DR SIDEWALK PH 2
Project Type: Sidewalk Projects
Project Manager:
David Andrews, Jr. - 407-665-5716
Status: Active
From: TUSKAWILLA RD
To: HOWELL CREEK BRIDGE
Scope: THIS PROJECT WILL CONSTRUCT APPROXIMATELY 3,100 LINEAR FEET OF SIDEWALK ON BOTH SIDES OF DYSON DR FROM TUSKAWILLA RD TO HOWELL CREEK. THE PROJECT INCLUDES DRAINAGE IMPROVEMENTS AND A NEW PEDESTRIAN BRIDGE OVER HOWELL CREEK.
Phases:
Construction Start: 6/2009 End: 10/2009
|
|
E LAKE MARY BLVD SIGNAGE
Project Type: Roadway Projects
Project Manager:
David Andrews, Jr. - 407-665-5716
Status: Active
From: AIRPORT ENTRANCE RD
To: SR 46
Scope: THIS PROJECT WILL DESIGN AND CONSTRUCT DIRECTIONAL SIGNAGE FOR AIRPORT ENTRANCE ON E LAKE MARY BLVD. THIS PROJECT IS RELATED TO CIP #010701 AND #010704.
Phases:
Design Start: 10/2008 End: 10/2008 Road Construction Start: 8/2009 End: 3/2010
|
|
EAGLE CIR AT DEER RUN SUBDIVISION RETROFIT
Project Type: Stormwater
Project Manager:
Rolando Raymundo - 407-665-5715
Status: Active
From: RED BUG LAKE RD
To: EAGLE CIR
Scope: PIPELINING FOR DEER RUN SUBDIVISION FROM RED BUD LAKE RD TO EAGLE CIR.
Phases:
Construction Start: 12/2009 End: 2/2010
|
|
ELDER CREEK AND ELDER RD SALES TAX CR 15 POND IMPROVEMENTS
Project Type: Stormwater
Project Manager:
Robert Walter - 407-665-5753
Status: Active
From: NARCISSUS AVE
To: CHURCH ST
Scope: PART 1. DESIGN AND CONSTRUCTION OF A REGIONAL STORMWATER POND ADDRESSING AREA FLOODING, PROVIDING WATER QUALITY TREATMENT, AND SERVING A SEGMENT OF CR 15. PART 2. ADDITIONAL 600 LINEAR FEET OF ROADWAY TO BE CONSTRUCTED.
FLORIDA DEPARTMENT OF ENVIORNMENTAL PROTECTION AGREEMENT # S0341
BCC DATE 08/28/07, ACTION # 38, FUNDING AGREEMENT
Phases:
Design Start: 1/2001 End: 6/2008 Land Start: 10/2003 End: 3/2006 Construction Start: 11/2007 End: 2/2008
|
|
FERNWOOD BLVD PEDESTRIAN CROSSING LOCAL AGENCY PARTICIPATION
Project Type: Sidewalk Projects
Project Manager:
David Martin - 407-665-5610
Status: Active
From: AT LYNX BUS STOP
To: AT LYNX BUS STOP
Scope: THIS PROJECT WILL DESIGN A RAISED PEDESTRIAN CROSSING 22 FEET IN WIDTH ACROSS THE EAST AND WEST BOUND LANES OF TRAFFIC ON FERNWOOD BLVD. THIS CROSSING WILL BE A SMOOTH UNIFORM, NON-SKID SURFACE OF CONTRASTING COLOR WITH 10` WIDE HIGH EMPHASIS CROSSWALK MARKING WITHIN THE CENTER 10 FEET OF THE CROSSING.
FLORIDA DEPARTMENT OF TRANSPORTATION AGREEMENT # APB 77
Phases:
Design Start: 3/2007 End: 9/2007 Road Construction Start: - End: -
|
|
GREENWOOD BLVD SIDEWALK
Project Type: Sidewalk Projects
Project Manager:
David Andrews, Jr. - 407-665-5716
Status: Active
From: LAKE EMMA ROAD
To: HEATHER DOWN LANE
Scope: CONSTRUCT SIDEWALK ON NORTH SIDE OF GREENWOOD BLVD. FROM LAKE EMMA RD TO 150` EAST OF PEBBLE CREEK CIRCLE & REPAIR EXISTING SIDEWALK FROM 150` EAST OF PEBBLE CREEK CIRCLE TO HEATHER DOWN LANE.
Phases:
Land Start: 10/2008 End: 10/2009 Construction Start: 1/2010 End: 3/2010
|
|
HOWELL BRANCH RD DETECTABLE WARNINGS
Project Type: Traffic Safety
Project Manager:
Melonie Barrington - 407-665-5676
Status: Active
From: SR 426
To: W TO COUNTY LINE
Scope: DETECTABLE WARNINGS. RECONSTRUCT 2 RAMPS AND INSTALL 31 TRUNCATED DOMES FOR ADA COMPLIANCE.
Phases:
Road Construction Start: 6/2009 End: 9/2009
|
|
HOWELL BRANCH RD LANDSCAPING
Project Type: Roadway Projects
Project Manager:
David Martin - 407-665-5610
Status: Active
From: LAKE HOWELL RD
To: SR 436
Scope: ADD LANDSCAPING TO ROADWAY PARCEL
Phases:
Road Construction Start: - End: -
|
|
HOWELL CREEK DAM AT LAKE HOWELL RD WATER CONTROL STRUCTURE
Project Type: Stormwater
Project Manager:
Rolando Raymundo - 407-665-5715
Status: Active
From: ORANGE COUNTY LINE
To: LAKE HOWELL RD
Scope: REPLACE EXISTING RUBBLE DAM WEST OF LAKE HOWELL RD.
NATURAL RESOURCES CONSERVATION SERVICE (NRCS)
AGREEMENT # 64-4209-9-1722
Phases:
Design Start: 12/2008 End: 12/2009 Construction Start: 4/2009 End: 7/2009 Road Construction Start: 4/2009 End: 12/2009
|
|
HUNT CLUB AT E WEKIVA TRL MAST ARMS
Project Type: Traffic
Project Manager:
Charles Wetzel III - 407-665-5686
Status: Active
From: N/A
To: N/A
Scope: CONVERSION OF AN EXISTING SPAN WIRE SIGNAL TO MAST ARMS.
Phases:
Road Construction Start: 1/2009 End: 8/2009
|
|
HUNT LN AT FOX RUN SUBDIVSION RETROFIT
Project Type: Stormwater
Project Manager:
Rolando Raymundo - 407-665-5715
Status: Active
From: PARK RD
To: FOX ROW AVE
Scope: DRAINAGE IMPROVEMENTS FOR FOX RUN SUBDIVISION FROM PARK RD TO FOX ROW AVE.
Phases:
Construction Start: 12/2009 End: 2/2010
|
|
IFAS MIDWAY REGIONAL STORMWATER FACILITY JOINT PARTICIPATION PROJECT
Project Type: Stormwater
Project Manager:
Robert Walter - 407-665-5753
Status: Active
From: CELERY AVE
To: SIPES AVE
Scope: DESIGN AND CONSTRUCTION OF A REGIONAL STORMWATER FACILITY PROVIDING FLOOD ATTENUATION AND WATER QUALITY TREATMENT FOR THE MIDWAY AREA. ALSO COMBINED WITH FLORIDA DEPARTMENT OF TRANSPORATION PROJECT SR 415.
ST JOHNS RIVER WATER MANAGEMENT DISTRICT
AGREEMENT # SJ456AA
ST JOHNS RIVER WATER MANAGEMENT DISTRICT
AGREEMENT # SI433AA
FLORIDA DEPARTMENT OF TRANSPORTATION
AGREEMENT # AP459
Phases:
Construction Start: 1/2009 End: 10/2009
|
|
IRON GATE CT AT MIDDLETON OAKS ASPHALT SURFACE AND PAVEMENT MANAGEMENT
Project Type: Paving
Project Manager:
Harry Raysin - 407-665-2839
Status: Active
From: OLD MAIL LN
To: CUL DE SAC
Scope: ASPHALT OVERLAY, FULL DEPTH RECLAMATION, AND VARIOUS METHODS OF ASPHALT SURFACE REFURBISHMENT THAT ARE APPLIED TO SEMINOLE COUNTY’S PAVED ROAD NETWORK. THIS INCLUDES LOCAL ROAD RESURFACING AND REHABILITATION THAT MAY INVOLVE RECONSTRUCTION ACTIVITY. THIS ALSO INCLUDES RESURFACING OF ARTERIAL/COLLECTOR ROADS NOT INVOLVING THE ROADWAY BASE.
Phases:
Construction Start: 10/2009 End: 9/2010
|
|
JAMESTOWN COMMUNITY SIDEWALK
Project Type: Sidewalk Projects
Project Manager:
Ken Mickenberg - 407-665-5714
Status: Active
From: VARIOUS LOCATIONS
To: VARIOUS LOCATIONS
Scope: THIS PROJECT WILL ADD SIDEWALKS TO THE JAMESTOWN COMMUNITY. THE LOCATIONS OF THE SIDEWALKS WILL BE DETERMINED AS PART OF THE DESIGN PROGRAMMED IN FY 2009/2010.
Phases:
Design Start: 4/2009 End: 12/2009 Construction Start: 1/2010 End: 4/2010
|
|
LAKE EMMA RD WIDEN FROM 2 TO 4 LANES
Project Type: Roadway Projects
Project Manager:
David Andrews, Jr. - 407-665-5716
Status: Active
From: SAND POND RD
To: LONGWOOD HILLS RD
Scope: THE ROADWAY WILL BE WIDENED FROM 2 TO 4 LANES. THE APPROXIMATE PROJECT LENGTH IS 2.0 MILES
Phases:
Design Start: 5/1996 End: 4/2009 Land Start: 2/2001 End: 6/2008 Road Construction Start: 11/2009 End: 12/2010
|