PROJECT ID |
|
|
AIRPORT BLVD SIDEWALK
Project Type: Sidewalk Projects
Project Manager:
Eric Erickson - 407-665-5666
Status: Active
From: US 17-92
To: SANFORD AVE
Scope: THIS PROJECT WILL CONSTRUCT 6,000 LINEAR FEET OF SIDEWALK, MISSING GAPS ON NORTHSIDE AND REPLACING CRACKED AND/OR SUB-STANDARD EXISTING SIDEWALK ON AIRPORT BLVD FROM U.S. HWY 17/92 TO SANFORD AVE.
Phases:
Design Start: 5/2008 End: 4/2009 Land Start: 4/2008 End: 12/2009 Construction Start: 10/2009 End: 3/2010
|
|
ALOMA AVE AT RED BUG LAKE RD PEDESTRIAN OVERPASS
Project Type: Overpasses
Project Manager:
David Martin - 407-665-5610
Status: Active
From: N/A
To: N/A
Scope: CONSTRUCT A PEDESTRIAN OVERPASS OVER RED BUG LAKE RD AT ALOMA AVE TO IMPROVE PEDESTRIAN SAFETY.
Phases:
Design Start: - End: - Construction Start: - End: -
|
|
ALTAMONTE CITY COUNTY SHARED PEDESTRIAN OVERPASS
Project Type: Roadway Projects
Project Manager:
Antoine Khoury - 407-665-5768
Status: Active
From: N/A
To: N/A
Scope: CITY OF ALTAMONTE SPRINGS PROJECT FOR PEDESTRIAN OVERPASS
Phases:
Road Construction Start: - End: -
|
|
ANCHOR RD DRAINAGE IMPROVEMENTS
Project Type: Stormwater
Project Manager:
Rolando Raymundo - 407-665-5715
Status: Active
From: SR 436
To: MELODY LN
Scope: DRAINAGE IMPROVEMENTS INCLUDING PIPING OF DITCH, INSTALLATION OF INLETS, AND WATER QUALITY TREATMENT. MISC. ROADWAY IMPROVEMENTS ALSO INCLUDED
Phases:
Design Start: 6/2005 End: 11/2008 Land Start: 2/2007 End: 9/2009 Construction Start: 12/2008 End: 1/2010
|
|
ARRA CROSS SEMINOLE TRAIL HOWELL CREEK TRESTLE
Project Type: Paving
Project Manager:
Mike Van Der Heyden - 407-665-5748
Status: Active
From: CROSS SEMINOLE TRAIL
To: HOWELL CREEK
Scope: THIS PROJECT WILL IMPROVE THE EXISTING STRUCTURE THROUGHT THE REPLACEMENT OF DETERIORATED BRIDGE SUBSTRUCTURE INCLUDING BRIDGE PILES, END BENTS, CROSS BRACING AND THE STABILIZATION OF THE SOIL RETAINING WALLS AT THE BRIDGE ENDS.
FLORIDA DEPARTMENT OF TRANSPORTATION
AGREEMENT # 4265801-1-58-01
Phases:
Road Construction Start: 12/2009 End: 2/2010
|
|
ARRA HOWELL BRANCH RD
Project Type: Paving
Project Manager:
Mike Van Der Heyden - 407-665-5748
Status: Active
From: COUNTY LINE
To: SR 436
Scope: THE OVERALL PROJECT WILL INCLUDE PAVEMENT REHABILITATION FOR HOWELL BRANCH ROAD PAVEMENT REHABILITATION - FROM COUNTY LINE TO ENSOR TERRACE FOR SEMINOLE COUNTY WHICH WILL INCLUDE MILLING AND RESURFACING ROADWAY SURFACE, INSTALLATION OF TRAFFIC SIGNAL LOOPS AND CONTROLS, AND REPLACEMENT PAVEMENT MARKINGS.
FLORIDA DEPARTMENT OF TRANSPORTATION
AGREEMENT # 426328-1-58-01
Phases:
Road Construction Start: 11/2009 End: 12/2009
|
|
ARRA LAKE MARY BLVD
Project Type: Paving
Project Manager:
Mike Van Der Heyden - 407-665-5748
Status: Active
From: MARKHAM WOODS RD
To: RINEHART RD
Scope: THE OVERALL PROJECT WILL INCLUDE PAVEMENT REHABILITATION FOR LAKE MARY BOULEVARD FROM MARKHAM WOODS ROAD TO RINEHART ROAD (BETWEEN INTERNATIONAL PARKWAY AND LAKE EMMA ROAD EXCLUDED) FOR SEMINOLE COUNTY WHICH WILL INCLUDE MILLING AND RESURFACING ROADWAY SURFACE, INSTALLATION OF TRAFFIC SIGNAL LOOPS AND CONTROLS, AND REPLACEMENT PAVEMENT MARKINGS.
FLORIDA DEPARTMENT OF TRANSPORTATION
AGREEMENT # 426324-2-58-01
Phases:
Road Construction Start: 12/2009 End: 1/2009
|
|
ARRA WEST 25TH ST PAVEMENT
Project Type: Paving
Project Manager:
Mike Van Der Heyden - 407-665-5748
Status: Active
From: OLD LAKE MARY RD
To: US 17-92
Scope: THE OVERALL PROJECT WILL INCLUDE PAYMENT REHABILITATION FROM OLD LAKE MARY RD TO US 17-92 FOR SEMINOLE COUNTY WHICH WILL INCLUDE MILLING AND RESURFACING. INSTALLATION OF TRAFFIC SIGNAL LOOPS AND CONTROLS, AND REPLACE PAVEMENT MARKINGS.
FLORIDA DEPARTMENT OF TRANSPORTATION
AGREEMENT # 426331-1-58-01
Phases:
Road Construction Start: 2/2009 End: 3/2010
|
|
ASPHALT SURFACE AND PAVEMENT MANAGEMENT
Project Type: Paving
Project Manager:
Harry Raysin - 407-665-2839
Status: Active
From: VARIOUS LOCATIONS
To: VARIOUS LOCATIONS
Scope: ASPHALT OVERLAY, FULL DEPTH RECLAMATION, AND VARIOUS METHODS OF ASPHALT SURFACE REFURBISHMENT THAT ARE APPLIED TO SEMINOLE COUNTY`S PAVED ROAD NETWORK. THIS INCLUDES LOCAL ROAD RESURFACING AND REHABILITATION THAT MAY INVOLVE RECONSTRUCTION ACTIVITY. THIS ALSO INCLUDES RESURFACING OF ARTERIAL/COLLECTOR ROADS NOT INVOLVING THE ROADWAY BASE.
|
|
BEAR GULLY LAKE ASSESSMENT
Project Type: Stormwater
Project Manager:
Kimberly Ornberg - 407-665-2417
Status: Active
From: BEAR GULLY LAKE
To: BEAR GULLY LAKE
Scope: LAKE ASSESSMENT.
|
|
BEAR LAKE RD AT BUNNELL RD MAST ARMS
Project Type: Traffic
Project Manager:
Charles Wetzel III - 407-665-5686
Status: Active
From: N/A
To: N/A
Scope: CONVERSION OF AN EXISTING SPAN WIRE SIGNAL TO MAST ARMS.
Phases:
Road Construction Start: 3/2009 End: 8/2009
|
|
BIG TREE PARK TRAILHEAD
Project Type: Trail Projects
Project Manager:
David Martin - 407-665-5610
Status: Active
From: BIG TREE PARK
To: BIG TREE PARK
Scope: DESIGN. PERMITTING, AND CONSTRUCTION OF A TRAILHEAD AT BIG TREE PARK.
FLORIDA DEPARTMENT OF ENVIRONMENTAL PROTECTION
AGREEMENT # T2705
Phases:
Design Start: 10/2007 End: 12/2009 Land Start: - End: - Construction Start: 2/2010 End: 6/2010
|
|
BIRD RD SIDEWALK
Project Type: Sidewalk Projects
Project Manager:
Eric Erickson - 407-665-5666
Status: Active
From: LAKE DR
To: SEVILLE CHASE DR
Scope: THIS PROJECT WILL CONSTRUCT APPROXIMATELY 2,500 LINEAR FEET OF SIDEWALK ON THE EAST SIDE OF BIRD RD FROM LAKE DR TO SEVILLE CHASE DR.
Phases:
Construction Start: 2/2010 End: 5/2010
|
|
BRIDGE REHABILITATION AND REPAIRS
Project Type: Roadway Projects
Project Manager:
Status: Active
From: COUNTYWIDE
To: COUNTYWIDE
Scope: THIS PROJECT TRACKS THE BRIDGE REHABILITATION AND REPAIR EXPENDITURES NECESSARY TO CORRECT DEFICIENCIES IN COUNTY MAINTAINED VEHICULAR BRIDGES THAT WERE IDENTIFIED AND REPORTED TO THE COUNTY BY THE STATE OF FLORIDA. THIS PROJECT ALSO TRACKS THE BRIDGE INSPECTION, REHABILITATION, AND REPAIR EXPENDITURES FOR ALL PEDESTRIAN OVERPASSES OR TUNNELS. THIS PROJECT RECEIVES NEW FUNDING OF $250,000 PER YEAR.
Phases:
Construction Start: 10/2009 End: 9/2014 Road Construction Start: 10/2008 End: 9/2013
|
|
BRUMLEY RD SIDEWALK
Project Type: Sidewalk Projects
Project Manager:
Ken Mickenberg - 407-665-5714
Status: Active
From: SNOW VALLEY WAY
To: AVENUE H
Scope: THIS PROJECT WILL CONSTRUCT APPROXIMATELY 1,400 LINEAR FEET OF SIDEWALK ON THE NORTH SIDE OF BRUMLEY RD BETWEEN SNOW VALLEY WAY AND AVENUE H. INCLUDING 600 LF ON THE WEST SIDE OF AVE. H FROM BRUMLEY RD TO SNOWHILL RD
Phases:
Construction Start: 6/2010 End: 7/2010
|
|
BUNNELL RD AND EDEN PARK AVE ROADWAY IMPROVEMENT PROJECT
Project Type: Roadway Projects
Project Manager:
Brett Blackadar - 407-665-5702
Status: Active
From: WEST TOWN PKWY
To: ORANGE COUNTY LINE
Scope: THE PROPOSED PROJECT WILL HAVE A CURB AND GUTTER SECTION WITH TWO TRAVEL LANES (ONE IN EACH DIRECTION) AND ONE 12-FOOT CENTER TURN LANE. THE APPROXIMATE PROJECT LENGTH IS 2.0 MILES
Phases:
Land Start: 4/2004 End: 6/2009 Road Construction Start: 1/2009 End: 4/2010
|
|
CASSEL CREEK STORMWATER FACILITY
Project Type: Stormwater
Project Manager:
Robert Walter - 407-665-5753
Status: Active
From: HOWELL CREEK BASIN
To: KEWANNE TR
Scope: 1.PRELIMINARY DESIGN OF REGIONAL STORMWATER FACILITY
2.FINAL DESIGN OF REGIONAL STORMWATER FACILITY.
ST JOHNS RIVER WATER MANAGEMENT DISTRICT
AGREEMENT # SG471AA
ST JOHNS RIVER WATER MANAGEMENT DISTRICT
ADDITIONAL ANTICIPATED AGREEMENT
Phases:
Design Start: 6/2004 End: 2/2010 Construction Start: 6/2010 End: 6/2011
|
|
CHAPMAN RD WIDEN FROM 2 TO 4 LANES
Project Type: Roadway Projects
Project Manager:
Antoine Khoury - 407-665-5768
Status: Active
From: SR 426
To: SR 434
Scope: THE PROJECT WILL WIDEN THE ROADWAY FROM TWO TO FOUR LANES. THE PROJECT LENGTH IS 1.7 MILES
Phases:
Design Start: 9/2006 End: 6/2008 Land Start: 3/2008 End: 12/2013 Road Construction Start: 5/2011 End: 4/2013
|
|
CLUB II REGIONAL STORMWATER FACILITY
Project Type: Stormwater
Project Manager:
Rolando Raymundo - 407-665-5715
Status: Monitoring
From: SR 46
To: WEST SIDE OF BRISSON AVE
Scope: PART 1. DESIGN OF A REGIONAL STORMWATER FACILITY ADDRESSING FLOOD ATTENUATION AND WATER QUALITY TREATMENT. THE PROJECT IS THE CONVERSION OF OVER 100 ACRES OF AN EXISTING BORROW PIT TO A REGIONAL STORMWATER FACILITY LOCATED WEST OF BRISSON AVENUE AND SOUTH OF FIRST DRIVE.
PART 2. CONCRETE PILING CLEAN UP.
PART 3. WATER QUALITY MONITORING.
FLORIDA DEPARTMENT OF ENVIRONMENTAL PROTECTION
AGREEMENT # S0163
|
|
CONTINENTAL BLVD AT COUNTRY CLUB HEIGHTS SUBDIVISION RETROFIT
Project Type: Stormwater
Project Manager:
Mark Flomerfelt - 407-665-5709
Status: Active
From: COUNTRY CLUB RD
To: CLYDE AVE
Scope: DRAINAGE WORK FOR COUNTRY CLUB HEIGHTS SUBDIVISION FROM COUNTRY CLUB RD TO CLYDE AVE.
Phases:
Construction Start: 12/2009 End: 2/2010
|
|
COUNTRY CLUB OR C-15 SIDEWALK
Project Type: Sidewalk Projects
Project Manager:
Eric Erickson - 407-665-5666
Status: Active
From: FREDERICK AVE
To: ALMA AVE
Scope: THIS PROJECT WILL CONSTRUCT APPROXIMATELY 1,000 LINEAR FEET OF SIDEWALK ON THE WEST SIDE OF COUNTRY CLUB RD FROM FREDERICK AVE TO ALMA AVE.
Phases:
Construction Start: 4/2010 End: 6/2010
|
|
COUNTRY CLUB RD ROADWAY REBUILD
Project Type: Roadway Projects
Project Manager:
Ken Mickenberg - 407-665-5714
Status: Active
From: RANTOUL LN
To: CR 46A
Scope: THIS PROJECT WILL REBUILD THE ROADWAY WITH DRAINAGE IMPROVEMENTS. THE PROJECT LENGTH IS APPROXIMATELY 1.3 MILES
Phases:
Design Start: 3/2008 End: 12/2008 Road Construction Start: 6/2009 End: 10/2009
|
|
COUNTY RD 46A SIDEWALK
Project Type: Sidewalk Projects
Project Manager:
Eric Erickson - 407-665-5666
Status: Active
From: RIDGEWOOD AVE.
To: US HWY 17-92
Scope: THIS PROJECT WILL CONSTRUCT 2,600 LINEAR FEET OF SIDEWALK ON THE SOUTH SIDE OF C.R. 46-A FROM THE SEMINOLE ANIMAL HOSPITAL TO OLD LAKE MARY ROAD AND FROM 400` WEST OF RIDGEWOOD AVENUE TO THE CITY OF SANFORD PARK
Phases:
Design Start: 1/2009 End: 12/2009 Land Start: 5/2008 End: 12/2009 Construction Start: 10/2009 End: 10/2009
|
|
COURTLAND LOOP CONSTRUCTION AT TUSKA BAY SUBDIVISION RETROFIT
Project Type: Stormwater
Project Manager:
Mark Flomerfelt - 407-665-5709
Status: Active
From: TUSKAWILLA RD
To: TUSKAWILLA RD
Scope: DRAINAGE IMPROVEMENTS FOR TUSKA BAY SUBDIVISION FROM TUSKAWILLA RD TO TUSKAWILLA RD.
Phases:
Construction Start: 1/2009 End: 12/2009
|
|
CR 15 WIDEN FROM 2 TO 5 LANES WITH BIDIRECTIONAL LANE
Project Type: Roadway Projects
Project Manager:
Brett Blackadar - 407-665-5702
Status: Active
From: SR 46
To: ORANGE BLVD
Scope: THE PROJECT WILL WIDEN THE ROADWAY FROM 2 TO 5 LANES WITH A BI-DIRECTIONAL CENTER TURN LANE. THE PROJECT LENGTH IS 1.2 MILES.
FLORIDA DEPARTMENT OF TRANSPORTATION AGREEMENT # AO977
BCC DATE 12/20/05, BCC ACTION # 48 FUNDING AGREEMENT
BCC DATE 09/11/07, BCC ACTION # 26, AMENDMENT I
Phases:
Design Start: 12/1999 End: 6/2007 Land Start: 2/2003 End: 12/2009 Construction Start: 1/2008 End: 7/2009 Road Construction Start: 1/2008 End: 7/2009
|