Pre-Power Electrical Inspections
Pre-power
requests will require only a single electrical
inspection by the County Electrical Inspector. Should
you have any questions concerning Pre-power,
please contact the Chief
Electrical Inspector.
The following
must be complete prior to pre-power being
approved:
- Pre-power form and fees paid ($60 plus all rejection
fees)
- The service
and that part of the electrical system
to be energized must be 100% complete
- Panels that
are to be energized must have their breakers
installed, wire pulled, and an electrical
inspection completed before it will be
energized
- The covers
on panels that are going to be energized,
breakers labeled (labels can be hand written
temporarily)
- Panels to be
locked or contained in a room that is locked
- the electrician and superintendent only
should have the keys
- All outlets
to be safed up either by installation of
device, equipment, or lighting fixture
or blanked off.
- Device covers
to be installed
- Each job will
be inspected on a case-by-case basis.
The electrical
inspector will inspect and either approve
for pre-power or reject for pre-power. If
you have problems or questions, please discuss
them with your site electrical inspector
or call the Chief
Electrical Inspector.