Steps |
|
Responsibility |
|
1. |
Request application and
procedures from the Program. |
Property Owners |
|
2. |
Complete and submit an
application with required application fee and
documentation. |
Property Owners |
|
3. |
Review the Application and
scope of services. |
Program & Engineering |
|
4. |
Provide initial cost estimate
of the requested improvement or service. |
Program & Engineering |
|
5. |
Review cost estimates and offer
detailed information regarding the requested
improvement or service. |
Program & Property Owners |
|
6. |
Submit payment for preliminary
engineering fees.
[Construction projects only] |
Property Owners |
|
7. |
Complete the Petition for
Improvement process. |
Program & Property Owners |
|
8. |
Hold First Public Hearing to
establish the MSBU.
[Adoption of ordinance] |
Program & BCC |
|
9. |
|
Implementation of the
project: |
|
. |
Obtain final engineering plans |
|
. |
Bid the construction |
|
. |
Construct the improvements |
|
| |
|
Engineering & Consulting |
|
Purchasing & Engineering |
|
Engineering & Contractor |
|
|
10. |
Hold Final Public Hearing to
establish the final costs and assessments.
[Construction projects only] |