Commercial
Irrigation
A site plan showing the location and size
of the existing watermain. Indicate whether
there is an existing service or if a wet tap
will be required. Also show the size and location
of the proposed meter and service line.
Submit irrigation calculations
showing annual average Gallons Per Day (gpd).
Show the number of heads per zone, gallons
per minute per head, zone run times, and
the days per week each zone will operate. Or,
the calculation can be based on an application
rate.
Reclaim Water
Irrigation
A site plan showing the location and size
of the existing reclaimed watermain. Indicate
whether there is an existing service or the
size of a wet tap if required. Also show the
size and location of the proposed meter and
service line. Service line and irrigation
pressure lines shall be color coded for reclaimed
water (Pantone Purple).
Submit a Reclaim
Water Application to the attention
of the One Stop Permitting Office in
the Environmental Services Department.
Temporary Construction
Meter
A site plan showing the location and size
of the existing watermain. Indicate whether
there is an existing service or the size of
a wet tap if required. Also show the size and
location of the proposed meter and service
line in relationship to the construction trailer.