Residential Permitting

Residential Permit Flowchart

Reviews are done concurrently. This flowchart is intended for a new structure.  If it is not a new structure the steps may vary slightly from this chart. The time frames in this flowchart are ONLY estimates and can vary according to the current workload.

Application Submittal
(1 day)
The application and other required documentation is submitted to the Building Department
CLICK HERE FOR MORE INFORMATION ON THIS STEP

Addressing
(1-2 days - if not in a platted sub)
The application is passed to addressing which will assign or verify an address for the 911 system.

Zoning Division
(1-2 days)
Zoning will review and verify the site and building plans for setback and any other land development requirements. Impact fees will also be set

Flood Prone Areas
(1-2 days - if required)
Flood Prone will review the application and inform or notify the applicant of any necessary requirements

Wetlands Areas
(2-3 days - if required)
Wetlands will review the application and inform or notify the applicant of any necessary requirements

Plan Review
(3-5 working days)
The plans will be reviewed. A list of inspections that will be required is relayed to the customer

Update and Issue
A permit tech will contact the customer with what fees they will need to pay and any items required prior to the permit being issued. The customer will come to the County Services Building to pay and will receive the permit.