Commercial Permitting

Caution IconReviews are done concurrently. This flowchart is intended for a new structure. If it is not a new structure the steps may vary slightly from this chart. The time frames in this flowchart are ONLY estimates and can vary according to the current workload.

Development Review Site Approval
Development Review will review, request changes, and approve the submitted plans
CLICK HERE FOR MORE INFORMATION ON THIS STEP

Blue Arrow Icon

Application Submittal
(1 day)
The application and other required documentation is submitted to the Building Department
CLICK HERE FOR MORE INFORMATION ON THIS STEP

Blue Arrow Icon

Addressing
(1-2 days)
The application is passed to addressing which will assign or verify an address for the 911 system.

Blue Arrow Icon

Development Review
Development Review will review and verify the plans are the same as in the first step

Blue Arrow Icon

Fire Review
(7-10 working days)
Fire review will review plans and inform the
customer of any required changes

Blue Arrow Icon

Commercial Plan Review
(7-10 working days)
Commercial Review will review the plans and inform the customer of any required changes

Blue Arrow Icon

Update and Issue
A permit tech will contact the customer with what fees they will need to pay and any items required prior to the permit being issued. The customer will come to the County Services Building to pay and will receive the permit.